LOAD TRANSFER SYSTEM ANALYSIS IN UNDERPINNING
Jouko Lehtonen LOAD TRANSFER SYSTEM ANALYSIS IN UNDERPINNING IWM Jouko Lehtonen
2
Duration of the underpinning project
INTRODUCTION The first analysis on load transfer system in underpinning was introduced by Dr Ismo Tawast, TUT 1993 The analysis has been updated and enlarged in the DATU project at Turku Polytechnic The load transfer system has many impacts to superstructures and implementation of underpinning Settlements Costs Duration of the underpinning project IWM Jouko Lehtonen
3
TOTALLY 9 DIFFERENT BASIC TYPES HAVE BEEN IDENTIFIED IN 2 CATEGORIES:
SETTLING SUPERSTRUCTURE NON-SETTLING SUPERSTRUCTURE IWM Jouko Lehtonen
4
SETTLING SUPERSTRUCTURE
IWM Jouko Lehtonen
5
Load transfer system No. 1
Column Wall IWM Jouko Lehtonen
6
Load transfer system No. 2
Column Wall IWM Jouko Lehtonen
7
Load transfer system No. 8
Column IWM Jouko Lehtonen
8
NON-SETTLING SUPERSTRUCTURE
IWM Jouko Lehtonen
9
Load transfer system No. 3
Column Wall IWM Jouko Lehtonen
10
Load transfer system No. 4
Column Wall IWM Jouko Lehtonen
11
Load transfer system No. 5
Column Wall IWM Jouko Lehtonen
12
Load transfer system No. 6
Column Wall IWM Jouko Lehtonen
13
Load transfer system No. 7
Column Wall IWM Jouko Lehtonen
14
Load transfer systems No. 9A and 9B
Column Column IWM Jouko Lehtonen