1
Centura Health Lawson 8 Upgrade
Upgrading from 7.2.2 to 8.x
2
Our Scope IN SCOPE: To upgrade the Lawson Applications to the latest version available from Lawson by using Lawson’s upgrade programs for upgrading from version 7.2 – 8.x. Review of all modified and custom Lawson programs to determine their future need and re-implement if necessary. Attribute Matrix will be implemented. We will migrate access to the Lawson 8.x applications from the desktop to web browser access for all employees OUT OF SCOPE: Lawson 8.0.x Environment. 7.2 – 8.x Must perform the cyclical first since we are on 7.2.2 Centura has approximately 300 mods Attribute Matrix benefits Centura due to the addition of account attributes
3
Project Team 3 Core Teams Materiels Management/Matching/AP
Financials (GL, AM, CB) HR/PR
4
Centura Health Lawson 8.x Upgrade Project Structure
5
Project Phases Planning Design Development Deployment
These phases are a combination of what Lawson recommends and the Microsoft methodology.
6
Planning Phase Kick-off Meeting with Teams
Risk Assessment & Mitigation Differences Training Technical Upgrade Training Hardware Requirements Differences Training was conducted in Lawson’s Training Data.
7
Design Phase Application Exploration (by Core Team)
Conference Room Pilot Preparation 1st Pass of Upgrade to be used in CRP Conference Room Pilot Risk Assessment & Mitigation Application Exploration was also conducted in Lawson’s Training Data, but would have been much more effective with Centura’s data. Programming has begun at this point…for CRP programs and then for others. Conference Room Pilot – 1 week per Core Team. Scheduling around getting everything into GL for close. CRP will not contain any testing of external interfaces only those internal to Lawson.
8
Development Phase 2nd Pass of Upgrade and System Testing
3rd Pass of Upgrade and System Testing Create Cutover Plan End User Training Plan Developed Risk Assessment & Mitigation Second Pass Testing will include all interfaces external to Lawson. All programming will need to be completed prior to our Third Pass. End User Training Plan Functionality between 7.2 & 8.x Navigation in browser
9
Deployment Phase Readiness Assessment End User Training
Risk Assessment & Mitigation Final Pass into Production
10
Topics for Discussion Third Party Reporting Report Smith & Access
Browser Access (NED vs. XML) Time frame for Cutover Hardware Considerations Functionality Differences Third Party Reporting Separate Core Team (members from all 3 core teams) Test daily/monthly/yearly production Report Smith and Access reports Repairing broken reports Test Lab Browser Access (Ned vs. XML) Hardware Considerations Disk Sizer Mark Deutsh IBM Review Can Oracle make the upgrade more efficient timewise? New machine scheduled for summer. Functionality Differences HR/PR – Not much – Exchange – CAN Currency is the big one – doesn’t affect us MM/AP – Matching re-write FIN – (AM) Balances stored by periods, Reinstate Disposals, Mass Adjustment (GL) Templates for subaccounts and Aus. Provides efficient way to add Aus and sub accts to another company. – this really doesn’t help us…but is a nice feature Ability to drill from AU to only those accounts that are active for that AU.
11
Tables Changes: Size % increase: 722 724 Tables 1.014 1.057
Indexes 722 Tables: Indexes: 3175 724 Tables: Indexes: 3299 802 Tables: Indexes: 4670 MSP 2 Added 3 Tables and changed 3. MSP 3 Added 2 Tables and changed 1.
12
LID: 722
13
LID: 724
14
LID: 802
15
NED: 802
16
XML: 802
17
XML: 802 Menu