1 Kolb Road Sabino Canyon to Sunrise Drive
September 20, 2018 CAC Update Meeting

2 Kolb Road Project Topics
Project Status Update Project Art Update Landscape Update Open Discussion Comments/Discussion

3 Project Status Update Final Plans Under Review
Artwork – Being Finalized Landscape - Being Finalized Major Utility Efforts Starting CenturyLink, SWG, TEP, Comcast, Tucson Water Right of Way Acquisition - Ongoing Federal Funding Authorization – Spring 2019 Project Bidding – Summer 2019 – Utility Relocation Driven Construction Kick Off Meeting – After Award

4 Project Art Update Same concept, new shape: an abstract, organic sculpture inspired by nature Placement: 3 large-sized shapes in roundabout and 2-3 smaller-size along Kolb next to sidewalks Medium: metal with mosaic inlay

5 Project Art Update Sample views:
Proposed size: large 11’ and small 5-7’

6 Landscape Update Landscape to feature native, low water use plantings
Plant palette based on native plants found on site Two example areas of landscape plan Proposed slope treatments and examples Collaboration with public artist at Roundabout

7 Landscape Update Landscape Palette

8 Landscape Update Landscape Plan Example Area

9 Landscape Update Landscape Section Example Area.

10 Landscape Update Landscape Plan Example Area

11 Landscape Update Landscape Section Example Area

12 Landscape Update Slope Treatments

13 Landscape Update Landscape Plan Roundabout Area

14 Landscape Update Landscape Plan Roundabout Area

15 Landscape Update Landscape Section Roundabout Area

16 Comments/Discussion