Marina-Salinas Multimodal Corridor Conceptual Plan
Fort Ord Reuse Authority January 10, 2013 Caltrans Grant Hired Kimley-Horn & Associates TAMC will manage the planning process and engage stakeholders and the public
2
Partner Agencies
3
Why? Congestion Safety Economy
4
Regional Context Marina Blanco Rd ADT: 23,100 Salinas
Hwy 68 ADT: 54,000
5
Project History Marina 1997 Base Reuse Plan Salinas
Agriculture Impacts Wildlife Habitat 2010 MOA CSUMB Impacts Terrain
6
Overview No new roads – only widen existing roadways.
7
? Project Scope Phase 1 - Alignment Which route?
Opportunities/Constraints Stakeholder Input Adopt Alignment ?
8
Project Scope Phase 2 – Corridor Elements
What will the corridor look like? What will it cost? Roadway Cross-Sections Intersections
9
Corridor Elements Focus on Bus Rapid Transit
Connections to Inter-regional transit such as the Salinas Rail Station
10
Study Area
11
Study Area
12
Project Schedule Kick-Off (Sept./Oct. 2013)
PH 1 Community Workshops (Feb2014) Adopt Preferred Alignment (Mar/April 2014) PH 2 Community Workshops (May/Jun 2014) Adopt Preferred Corridor Elements (Jul/Aug 2014) Adopt Final Conceptual Plan (Oct. 2014)
13
Questions? Ariana Green Project Manager 831-775-4403