1
Success in Exporting BHA Annual Conference 2012
2
SME established in 1991 Engineering Consultancy with 30 Engineers We specialise in Hydraulic Steel Structures for: Hydro Power River Control and Flood Defence Leisure Marinas Commercial Docks & Harbours In addition to; Moving Bridges and Linkspans Special Purpose Machinery
3
Office Locations Poole Suite 4, Bourne Gate, Bourne Valley Road, Poole BH12 1DY Tel: +44 (01202) 311766 Fax: +44 (01202) 318472 www.kgal.co.uk Wakefield 16 Appleton Court Calder Park Wakefield WF2 7AR Gloucester The Small Barn, Marina Walk Offices, Walk Farm, Frampton on Severn GL2 7PR
4
Typical UK Projects
5
Hydro Power Replacement of Reservoir Regulating Spillway Radial Gates
6
Flood Defence River Hull Tidal Surge Barrier 30m Clear Span x 10.7m Deep x 220 Tonnes
7
Leisure Marina Sector Lock Gates – Swansea Marina
8
Commercial Docks and Harbours Port of Barrow Mitre Gates 460 Tonnes Fabrication
9
Special Purpose Machinery Falkirk Wheel Exemplar Design and Performance Specification
10
Previous export projects in; India Mexico Thailand Oman Korea Vietnam Brunei USA Current export projects in; Australia Laos
11
Xayaburi Hydro Electric Power Project Laos
12
Location of Site
13
Owner – Xayaburi Power Co. (J.V. between GOL & C.H.Karnchang Constn) GOL Engineer - Poyry Main Contractor – C.H.Karnchang 30 Year B.O.T.
14
1285 MW Run of River 8 Kaplan Turbines 7 x Power for Export 1 x Power for Laos
15
Early impression of barrage Looking Up Stream
16
Location of Barrage – June 2012 Dry Season
17
Location of Barrage – August 2012 Wet Season
18
Close up – June 2012 Dry Season
19
Close up – August 2012 Wet Season
20
Remote location of barrage Difficult access to site New main access roads going in
21
Remote location of barrage Until then: Every visit is an adventure!!
22
Layout of Barrage
23
Main Components of the Barrage Navigation Lock Spillway Power House Fish Pass
24
Package 1 – Civil Works C.H.Karnchang AF Consult + Team Consult Package 2 – Hydro mechanical Whessoe Sdn.Bhd. + KGAL Package 3 – Electro mechanical TBC
25
Package 2 – Hydro mechanical Whessoe Sdn.Bhd. Manufacture, Installation and Commissioning KGAL Design, Quality Surveillance, Technical Support, Site Supervision
26
KGAL Scope on the Barrage Design of Hydraulic Steel Structures including; 7x Spillway Radial Gates 19m Span x 25m High 4x Flushing Radial Gates 12m Span x 16m High 3x Nav Lock Mitre Gates 12m Span x 30m High 23x Power Intake Gates 7m Span x 18m High 23x Power Intake Screens 7m Span x 45m High 23x Draft Tube Gates 7m Span x 12m High 14x Sand Flushing Gates 4m Span x 6m High 71 Gates of Varying sizes for the Fishpass System Fishpass Pumping System Numerous Lock Filling Sluice Gates Small Boat Lift & Transfer System for Navigation Lock
27
Section Through Main Spillway Radial Gate 19m Span x 25m High
28
Solid Model of Flushing Radial Gate 12m Span x 16m High
29
Solid Model of Mitre Lock Gates 12m Span x 30m High
30
Seismic Analysis of Mitre Lock Gates 12m Span x 30m High
31
Seismic Analysis of Mitre Lock Gates 12m Span x 30m High
32
KGAL Scope on the Barrage In excess of 30,000 man hours UK design work Seismic assessment of all gates in accordance with the latest ICOLD Requirements Quality surveillance of local fabrication drawing office Sign off of all fabrication drawings Quality surveillance of manufacture at site facility Technical support and supervision of site installation
33
KGAL programme of works Duration of UK design work – Years 1 to 3 Drawing office quality surveillance – Years 1 to 3 Manufacture quality surveillance – Years 2 to 4 Technical support for site works – Years 2 to 6
34
Xayaburi Current status of Site construction
35
Everything comes in by haul road
36
New site access roads and accommodation
37
Main site office comlex
38
Early excavations adjacent to the River for the Navigation lock and Spillway
39
Excavation and foundations for Whessoe site fabrication facility
40
Very little flat land available Fabrication shop will be 300m Long
41
Summary It is possible to reverse the trend and win export work Market place is difficult and competitive UK no longer regarded the leader in Hydropower Financial support no longer available from UKTI Websites provide access to World Market Essential to get out and meet people BHA provide a very cost effective way to do it Hydro 2012 next week in Bilbao Hydro 2013 will be held in Innsbruck