Off Shore Platform Modularization
Necessity, Not An Option
2
Necessity? Consider The Job Site Green Field Brown Field Blue Field
- 2
3
Blue Field Job Site
4
What Is In An Off Shore Platform?
7 Decks 10 Packages Decks Cellar L Mezzanine Production U Mezzanine Weather Drilling Heli Deck Skid Base Drilling PKG Pipe Barn Generator Bldg Living Qtrs Flare Boom Stair Tower Pedestal Crane Bridge Cap DSF
5
Modular Build By Deck By Blocks Per Deck Bottom Up – Literally
6
Assembly Sequence - 6
7
Assembly - 7
8
GBS Site – Tower Crane View
. GBS Site – Tower Crane View Top of A53 Shaft A51 Cover Deck Installed A54 Shaft, DCL
9
. LMD PE Pre-Erection Block 32B - Outfitting
LMD PE Pre-Erection Block 33D - Outfitting LMD PE Pre-Erection Block 33E - Outfitting CD Mechanical Installation and Outfitting
10
Modular Installation GBS Topsides
11
Installation
12
Off Shore Platform Modularization
The End