Download presentation
Presentation is loading. Please wait.
1
Cycle Time Efficiency Model
By: Mike Kenefsky, PM Vitals
2
About PM Vitals PM Vitals is a “Software as a Service” (SaaS) business made up of project administration experts (accounting, data management, project management, project controls, scheduling, supply chain management and safety management) PM Vitals provides project specific software solutions for complex EPC/CM capital projects throughout the lifespan of a project
3
Dynamics of a Complex EPC/CM Environment
Heavily regulated by government agencies High level of quality standards Multi-tiered suppliers/subcontractors influencing major scopes of work Technically sophisticated design High level of oversight/involvement by all parties …just to name a few
4
Industry Challenges & Pitfalls
Deployment of infrastructure in short window of time Overwhelmed by project complexity Limitation of time to perform critical analysis Pitfalls Recognizing risks early Prioritizing work activities Undertaking opportunities to improve
5
Project Objectives Determine the cycle time required to support a given process activity accounting for all downstream work activities and risk items Evaluate how an integrated systems approach may optimize a savings, in time, for a process, project &/or business (prospective client) Standardize the simulation to be applied for future projects Because of these challenges and pitfalls, it seems apparent that we can make up some ground here. I chose to analyze work process activities and my objectives were to:
6
Project Activities & Tasks
Identify Direct Process Activity Determine Objective (minimize time, minimize cost, etc.) Model Process Workflow Gather Data for Each Process Activity Verify Accuracy of Process, Process Work Activity Durations, Likelihood of Occurrence & Risk Items Perform Simulation Using Monte Carlo Model Analyze Results and Apply PM Vitals’ Efficiency Influence Factor to Achieve Objectives
7
RFI Initiation and Downstream Process Activities
RFI Assembly & RFI Response Design Change Issued (tech) Change Order Issued (vendor contract) Fab Detail Review/Approval Fabrication Shipment Receiving Terms & Graphical Legend Process Work Step (detail work steps not shown in graphic) Process Duration Process Model (overall sequence of related processes) Probability Branch (reflects chance of process path deviation) Risk Item (reflects likelihood of known unknowns occurring) Base Parameters Fabricated item involved
8
RFI Initiation and Downstream Process Activities
RFI Assembly & RFI Response ex: Is this the right location? (60%) No Further Action required ex: Yes, proceed accordingly (40%) Design Change Required ex: No, a change is forthcoming Design Change Issued (tech) ex: Correct location defined (40%) No Further Action required ex: New location impacts dimensions (60%) Change Order Required Change Order Issued (vendor contract) ex: Vendor notified ex: Vendor submits product data of new panel Fab Detail Review/Approval (10%) No Further Action required ex: Client has panel in stock (90%) Fabrication Required ex: Panel fabricated by supplier Fabrication Shipment Receiving (10%) Misfabricated Items (20%) Delivery Delay (10%) Nonconformance Identified Terms & Graphical Legend Process Work Step (detail work steps not shown in graphic) Process Duration Process Model (overall sequence of related processes) Probability Branch (reflects chance of process path deviation) Risk Item (reflects likelihood of known unknowns occurring) Base Parameters Fabricated item involved
9
RFI Initiation and Downstream Process Activities
RFI Assembly & RFI Response Determine “Direct” Utilization of personnel versus “Indirect” Utilization “Direct” utilization includes personnel physically working to support a process activity “Indirect” utilization includes time between “Direct” work activities between work queues and between organizations (60%) No Further Action required (40%) Design Change Required Design Change Issued (tech) (40%) No Further Action required (60%) Change Order Required Change Order Issued (vendor contract) Fab Detail Review/Approval (10%) No Further Action required (90%) Fabrication Required Fabrication Shipment Receiving (10%) Misfabricated Items Indirect Utilization Direct Utilization (20%) Delivery Delay (10%) Nonconformance Identified Terms & Graphical Legend Process Work Step (detail work steps not shown in graphic) Process Duration Process Model (overall sequence of related processes) Probability Branch (reflects chance of process path deviation) Risk Item (reflects likelihood of known unknowns occurring) Base Parameters Safety Significant item involved
10
P LA Y
11
Confidence Interval of 90%... 175 Days!
Simulation Results Direct Work Activity Total Cycle Time Downstream Work Indirect Work Confidence Interval of 90% Days! Risk Items
12
PM Vitals’ Influence Efficiency Factor: 40%
13
Conclusions & Recommendations
Interdependencies of process activities must be considered when planning work effectively Majority of time is spent supporting indirect “non-utilized” process work activities PM Vitals to use this model to discuss with prospective clients how integrated solutions can improve a complex project schedule Failure to integrate the project team at all levels of the supply chain exposes project to ineffective planning initiatives, increased schedule delays, and additional costs Recommendations PM Vitals to use the simulation model as a continuous improvement initiative for current clients
14
Questions & Answers
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.