Domino.Doc Project Overview Project Rollout/Schedule Preview Eastman Kodak Health Imaging Doug Smith
2
Project Goals Corporate Deployment of Lotus Domino for DHF/21CFR11 Submissions Phase One - Migration of Design History Files to Louts Notes Phase Two – define next component to be rolled out, electronic signature
3
General Description Identify the desired forms and workflow for sites. Create migration path for existing DHF database. Training and User Documentation FOR MORE INFO... Contact: Jeff B.
4
Core Technology Used Identify new technology being used –Why existing system needs upgrade Quality Standards supported –Connect to Quality Section Number Other technology options evaluated –Microsoft Content Server
5
Team/Resources Assumptions about resources allocated to this project: –4 Allendale R&D resources –1 Dallas R&D resources –4 Regional site liaisons –Technical support & outside services FOR MORE INFO... Contact: Doug S.
6
Procedures Highlight any procedural differences from regular projects of this type Discuss how user training and documentation is provided First and Second level technical support tiers FOR MORE INFO... Contact: Rolando S.
7
High Level Milestones Review high-level milestones: FOR MORE INFO... Visit the Project Database on Notes
8
Current Status Gate zero scheduled 3/18/03 ( firm ) –Platform development proceeding –Site requirements not defined –CRD not yet started Projecting about 1w late at Gate 0/LCA due to CRD. FOR MORE INFO... Contact: Doug S.
9
Project Metrics Collection Plan There are standard project metrics for all EK projects as described in the SOP 1F2236 that will be collected: Software Development Cost and Effort Software Project Schedule Progress Software Product Quality Software Product Functionality Software Product Performance goals FOR MORE INFO... Contact: Jeff B.
10
Related Documents Marketing plan waived in PDP Budget - small budget model applies Staffing plan contained in PDP WAIS Development Process with RUP phased rollout FOR MORE INFO... Contact: Tim L.
11
Cost and Time Summary Direct Labor costs: $ 142,140.62 Capital costs not in this schedule Project Duration: 126 days Final delivery date: 5/22/03 Feature count: TBD Contact: Doug S. FOR MORE INFO...
12
Rollout Schedule-Overview All development/testing is for Gate 1/LCA Gate 2/3 is documentation/PR.
13
Gate 0 - Planning Phase Team is formed, gate 0 work 63% complete and on schedule for 3/11/03 gate zero. Collection of site requirements is on schedule.
14
Gate Zero – Platform Definition Platform definition due 3/5/03 Running in parallel with site requirements.
15
Gate Zero – Process Documents Back loaded from 3/18/03 G0 date Runs in parallel with site requirements.
16
Gate One – Rapid Prototyping Engineering prototype due by 3/25 Gate two documents planned back from 5/30. Developers allocated at only 60%
17
Gate One – Documents Documents due 5/9 for 5/13 G1 Substantially all development/test complete
18
Gate Two – Documents Documents only, combine G2 and G3 ? No development planned/test complete
19
Rollout Schedule-Gate Three No development, just documentation Duration fixed primarily by resource constraints Schedule can be improved with TKM support
20
Rollout Schedule-Phases Gate targets at the top for visibility Major start dates shown below
21
Project Reporting Structure Weekly schedule update on Fridays Weekly in-process task list to Jeff Schedule distributed within R&D team. Post schedule changes as responses to the schedule itself in the Project Database.
22
Conclusions Assumes all non-project activity does not exceed 40% - OK Detail on the site rollout in Program Plan but not schedule Assumes no scope creep G2+ since no development is scheduled