1 Update to Loxahatchee River Coordinating Council
L-8 Reservoir Water Quality Flow-way 1 Water Delivery Test G-92 Structure Replacement September 29, 2008

2 L-8 Reservoir – August 2007

3 Parameters (Cell 3) Sampling Depth 0.5 m 6.5 m 12.5m Temperature 27.7 23.4 21.9 D.O. 8.83 6.79 4.39 Specific Conductance 2853 2817 2816 pH 8.3 8.1 7.8 TSS <3 TDS 1649 1644 1328 TKN .81 .97 .87 Tot. Kjeldahl N 0.81 0.97 0.87 Nitrate/Nitrite <0.005 0.123 0.130 Ammonia Total Phosphorus 0.006 0.008 0.023 Ortho-Phosphorus 0.002 0.005 Chlorides 442 614 633 Sulfate 165 229 236

4 0.5 m 6.5 m 12.5m Parameters (Cell 6) Sampling Depth Temperature 27.9
23.4 22.3 D.O. 10 7.36 5.01 Specific Conductance 3801 3809 3835 pH 7.9 7.7 7.6 TSS 5 3 <3 TDS 2275 2247 2317 TKN 1.12 1.07 1.15 Tot. Kjeldahl N 1.0 0.86 0.84 Nitrate/Nitrite 0.118 0.206 0.308 Ammonia <0.005 0.009 Total Phosphorus 0.010 0.018 0.022 Ortho-Phosphorus <0.002 Chlorides 943 895 914 Sulfate 347 329 334

5 Results Similar to historical for WY 05 – WY 08
Lower concentrations of nutrients in cells than in either L-8 or M-Canal No metals exceeded WQ criteria Class I/III criteria exceeded for: Specific conductance, TDS, Chlorides and Gross Alpha Levels comparable to current cell historical levels – levels of parameters in exceedence are expected to decrease as reservoir is operated

6 Mixing Zone Boundaries
Site Unit n Average Minimum Maximum L8MZBN µS/cm 20 768 489 978 L8MZBS 569 480 695

7 FLOW-WAY 1 TEST PURPOSE: To test water delivery from the regional water system to the Loxahatchee River Basin using the existing infrastructure TEST DATE - July 1 – July 3, 2008

8 Grassy Waters Preserve – M Canal
Flow-way #1 G-160 Northlake Bridge Control #2 Pump Station G-161 M Canal Widening Grassy Waters Preserve – M Canal

9 TEST CRITERIA Establish baseline stages/flow rating curves
Control GWP releases to limit effect on apple snails Release ~150 cfs at Control 2, 100 cfs at G-161, 100 cfs to NWFLR Maintain appropriate stages at GWP, G-161 and G-160 Ensure coordination with stakeholders Measure water flow at critical locations Obtain water quality samples during test

10

11 Calculated Daily average flow (cfs)
RESULTS DATE Calculated Daily average flow (cfs) CTRL 2 G-161 G-160 G-92 Lainhart Dam 7/1/08 147 41 73 110 128 7/2/08 91 160 138 200 7/3/08 143 50 206 71 215

12 Measured Flows DATE Flow Station Ctrl 2 G-161 G-160 E. Perimeter Canal
7/2/08 150 - 100 35 7/3/08 95 80

13 Measured Avg. Daily Water Levels
DATE Stage Elevation (feet NGVD) GWP (G-161 HW) G-161 TW G-160 HW 7/1/08 18.18 16.14 15.03 7/2/08 18.04 17.12 15.13 7/3/08 18.15 17.10 14.98

14 Conclusions Confirmed that if replacement water is available, structures can be operated to deliver flow Confirmed 150 cfs at control 2, but only 35 cfs at E. perimeter canal G-161 operated to deliver 100 cfs to C-18 Flow to NWFLR exceeded 100 cfs during test period Each structure is critical and operation must be synchronized to achieve results Measured flows agreed with estimated

15 G-92 Structure Replacement

16 G-92 Structure Proposed Design & Location
New in-kind (single barrel, box culvert) will be installed to maintain flood protection and conveyance Located adjacent to existing structure Existing structure to be demolished

17 G-92 Structure Background
Structure supplies water from the C-18 canal to the Loxahatchee River via the South Indian River Drainage District canal C-14 Erosion and structure deterioration has limited structure capacity Failure of the existing structure became critical during 2004 hurricane season

18 G-92 Structure Benefits of New Structure
Reliability Extended service life Remote operation Public safety Flood protection Water delivery

19 G-92 Structure Operation
New structure will not deviate from existing operational criteria. Remote operation through telemetry

20 G-92 Structure Replacement Schedule
Bid opening scheduled for September 29, 2008 at 2:30 p.m. Construction start – late November to early December 2008 Construction time frame days