Download presentation
Presentation is loading. Please wait.
1
Risk management
2
Definitions of risk General: standard deviation
Finance: volatility of return(s) and costs Risk in project management (Lockyer – Gordon): An uncertain event or set of circumstances that, should it occur, will have an effect on the achievement of the project objectives (prevent it proceeding according to the plan). The effect may be detrimental or present an unforeseen opportunity.
3
Uncertainty vs. risk Uncertainty: when neither the possible events nor their possibilities are known. Risk: when both the possible events and their possibilities are known Uncertainty is worse than risk Reducing uncertainty reduces risk
4
Importance of risk management
In relatively a stable and simple environment: Risks tend to be small Risk management is a part of task management In changing environment: Significant uncertainty and thus risk If there is uniqueness in the work, manageing risk is harder Risk management is not an option but an essential part of management
5
Sources of risk Timing Technology People Finance Managerial Political
6
Risk from timing All project activities are concerned
Two categories of activities for risk minimisation: Internally timed activities: the task owner is responsible for carrying out the activity duration estimation is done by the project team sources of information are past experience of similar work knowledge/hunches of the project team: good communication is needed external sources, secondary information Externally timed activities
7
Externally timed activities
Where some outside body sets the duration The responsibility is of the procurement executive After the order is placed, the delivery dates should be secured: Systematic monitoring Delivery performance must be recorded in the project log
8
Risk from technology The newer the technology, the greater the uncertainty and thus the risk New application of a tested technology increase the risk, too
9
Risk from people Depends on people’s skill, experience and motivation
This type of risk an be reduced by: Good communications Clear definition of tasks Good training: preparing the team
10
Risk from finance Financial stability at every party involved
Stability of suppliers should be investigated by the procurement executive
11
Managerial risk Delegation: Does the project manager and other team members have the authority to effectively deal with every problem? (especially with cross-functional problems) Intervening after delegation can be unnecessary and a source of conflict Project manager has to authorized by the top management, others by the project manager.
12
Political risk Organisational politics of the parent organisation
International and national politics Sometimes the distance increases the uncertainty
13
Steps of risk management
Risk identification Creating a risk register Assess and evaluate risks (and secondary risks) Response to risk Risk mitigation Risk management plan
14
Risk identification For the whole project lifetime
Try to identify as many areas of uncertainty as possible (build up a risk register) Develop uncertainty into risks (probability, impact) A network plan can help the identification Rank the risks in order of seriousness
15
Uncertainty can give rise to benefits as well as adverse effects.
Risk assessment Two separate components: Quantitatively assessment: Statistical analysis (using past data to reveal the underlying model) Subjective (human risk) assessment Harder to assess and quantify Two perception: Project manager Project sponsor Uncertainty can give rise to benefits as well as adverse effects.
16
Fundamental questions of risk identification and analysis
What could go wrong? Techniques: Brainstorming Experience of past projects Project networks (sources of risks & float time for mitigation) How likely it is (possibility)? How will it affect the project (impact)?
17
Risk register List of identified risks
Explanation of the nature of each risk & the extent of damage or opportunity Assessment: Quantifying by assessing the probability Sorting by the size of the problem: high, medium, low Management methods or plans for each risk Be aware of secondary risks: efforts to manage the primary problem can lead to a new one
18
Response to risk A part of the risk management plan
Must deal with every identified risks Modify the project objectives Use alternative technologies or methods Use alternative project management Increase managerial strength Reduce interdependency Increase resources Increasing flexibility
19
Risk mitigation techniques
Risk transfer: to someone more capable (insurance is the simplest) Risk deferral: moving risk in time Risk reduction: Probability Impact Risk acceptance: reserve or contingency plan Risk avoidance: replace the risky activity
23
Reading Textbook chapter 7
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.