Presentation is loading. Please wait.

Presentation is loading. Please wait.

Kaituna River Re-diversion and Te Awa o Ngatoroirangi / Maketū Estuary Enhancement Project 7 November 2018 Community Meeting Murray Brock video.

Similar presentations


Presentation on theme: "Kaituna River Re-diversion and Te Awa o Ngatoroirangi / Maketū Estuary Enhancement Project 7 November 2018 Community Meeting Murray Brock video."— Presentation transcript:

1 Kaituna River Re-diversion and Te Awa o Ngatoroirangi / Maketū Estuary Enhancement Project 7 November 2018 Community Meeting Murray Brock video

2 Meeting agenda Background to project What has been done since August? What work is planned? How will that affect you? He patai / questions

3 Background

4

5 To significantly increase the volume of water (particularly fresh water) flowing from the Kaituna River into Ongatoro/Maketu Estuary by 2018 in a way that maximises the ecological and cultural benefits (particularly wetlands and kaimoana) while limiting the economic cost and adverse environmental effects to acceptable levels 20% of river flow + 20 ha new wetlands

6 Progress report Construction started 12 June 2018
Scheduled completion 30 June 2018 29% complete as at 31 October 2018 12,000 worker hours so far

7 Recent actions Dredging Temporary and permanent sheet piling
Ford Rd culvert removal First concrete pour complete Stage 1 new stopbank complete RL 2.2m Ford’s Cut widening Te Pā Ika wetland shaping Stopbank ‘overlay’ placement Salinity block pushed out 60m

8 Work done since August 2018 Flyover video
In 2016 the blessing for the commencement of the works was finally held. Tangata whenua groups have worked alongside regional council to support the works. Flyover video

9 What work is planned? Finish dredging Finish sheet piling
Pour concrete and install 12 culverts Strip and excavate new channel Te Pā Ika wetland shaping Ford’s Cut widening Import rip-rap rock and place in new channel

10 How will you be affected?
Ford Rd will reopen to the public from 20 December From 8 February it will be open 7pm – 7am, but closed during the day The boat ramp will be closed until 2020 Alternative boat ramps at Bell Rd and Maketū Roading effects, 75% of material has now been imported

11 He patai, any questions? In 2016 the blessing for the commencement of the works was finally held. Tangata whenua groups have worked alongside regional council to support the works.


Download ppt "Kaituna River Re-diversion and Te Awa o Ngatoroirangi / Maketū Estuary Enhancement Project 7 November 2018 Community Meeting Murray Brock video."

Similar presentations


Ads by Google