Download presentation
Presentation is loading. Please wait.
Published byDulcie May Edwards Modified over 5 years ago
1
The Improvement of ALARA for the Steam Generator Maintenance
Radiation Safety Department The 3rd Plant, Ulchin Nuclear Power Site
2
CONTENTS ■ Background ■ Summary ■ Review of ALARA ■ The main improvements and effects ■ Conclusions
3
maintenance during the 2nd overhaul of Ulchin Unit 5 in 2006.
BACKGROUND ■ ALARA performed focusing on the SG maintenance during the 2nd overhaul of Ulchin Unit 5 in 2006. ● the highest occupational exposure ● the greatest spread of contamination ● in particular with poor radiation work environment
4
SUMMARY ■ Flow chart of SG Maintenance
5
SUMMARY ■ Radiation work dose
● work duration : 9/11/2006~10/4/2006 (24 days) ● workers : 92 persons (932 man-days) ● radiation dose - Individual dose [mSv/person] limit average maximum remarks work dose accumulated dose 16 (20*) 0.55 3.61 15.31 worker of ECT * regulatory limits
6
SUMMARY - Collective dose (man-mSv) SG maintenance planned real
remarks manway (open/close) 9 6.58 - 2.42 nozzle dam (install/remove) 8.86 - 0.14 ECT 38.5 28.02 lancing & FOSAR 12 6.25 - 5.75 total 69.5 49.71 * ECT maintenance dose was 16.6% of the total dose for overhaul (298.7 man-mSv/34days)
7
REVIEW OF ALARA ■ SG cooling method before the year 2006
● Tube and chamber cooled and dried by air blower after reactor coolant water made them cooled - Took a long time to reach the proper temperature (about 30℃) - The maintenance should be performed in the work environment with high temperature and humidity to meet the overhaul schedule. ● The temporary manway cover did not completely seal the hole of SG manway due to a decrease the function of the air blower to dry and purify the contamination and humidified air inside SG tube.
8
REVIEW OF ALARA ■ Radiation protection ● Work planning
● Source of radiation ● Protection of radiation worker ● Area contamination control ● Environmental condition of work place
9
THE MAIN IMPROVEMENTS & EFFECTS
■ Efficient maintenance minimized the radiation dose by modifying the cooling method of SG ● Cooling to utilize the heat exchanger of the SG blow down system - cooling time : about 46 hours - outlet temp of cooling water : 15℃ ● Installing the manway temporary cover-only to seal the hole of SG manway (hot leg and cold leg) - dimension : (dia.) 700 × (T) 3 mm - air exhaust hole : (dia.) 50 × (H) 80 mm - spray nozzle hole : (dia.) 50 × (T) 2 mm - material : SS304
10
THE MAIN IMPROVEMENTS & EFFECTS
■ Cooling Flow
11
THE MAIN IMPROVEMENTS & EFFECTS
■ The manway temporary cover-only BEFORE AFTER
12
THE MAIN IMPROVEMENTS & EFFECTS
■ Results ● Optimization of working environment - working hours were shorter and the troubles of ECT equipment were less than those of the previous SG maintenance ● Comparison to 2005 items 2005 (the 1st OH) 2006 (the 2nd OH) remarks work duration 18 days 14 days - 4 days temperature in chamber about 80℃ less than 30 ℃ - 50 ℃ replacement of ECT probe 176 ea 117 ea - 59 ea work dose [man-mSv] 72.07 49.71
13
THE MAIN IMPROVEMENTS & EFFECTS
■ Reduction of radiation dose and prevention of contamination ● Dose rate reduction of work area ◆ shielded the hot spot (manway retainer plate) with lead blanket - before shielding : 4.0 mSv/hr - after shielding : 0.9 mSv/hr ◆ put the high radiation waste probe into the lead shield cask promptly and dispatched the cask to the temporary stored area. ◆ decontaminated quickly when the surface over the work area was contaminated from the high contaminations such as the sludge of the waste ECT equipment probe.
14
THE MAIN IMPROVEMENTS & EFFECTS
■ Prevention of internal and external contamination ● worn respirator - air supplied respirator for jumper - full-face mask for ECT and manway working ● should not touch own face and head ■ Preventing the spread of contamination ● wore the safety shoes for work place-only ● kept the step barrier when going in and out ● monitored the trend of surface contamination level and air borne activity ● used the tools and equipment with proper packing, and installed the cable for ECT to the upper side ● periodically checked contamination of safety shoes and exchanged as necessary ■ Decontaminated and cleaned overall area such as floor, pipes, grating etc in the end of overhaul
15
CONCLUSIONS in radiation dose as well as raising the quality of
■ Our plant could successfully achieve the reduction in radiation dose as well as raising the quality of maintenance by optimizing the work environment such as improvement of the SG cooling method, and decreasing the dose rate of work area. ■ Preventing the spread of contamination through absolute analysis for ALARA from the preparation to the beginning of SG maintenance.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.