1 1 Pre Bid Conference JGB Lobby Level Meeting Room December 12, 2012 9:00 am IFB FQ12210 Rehabilitation of Parking Garages at Vienna (South), Southern.

Similar presentations


Presentation on theme: "1 1 Pre Bid Conference JGB Lobby Level Meeting Room December 12, 2012 9:00 am IFB FQ12210 Rehabilitation of Parking Garages at Vienna (South), Southern."— Presentation transcript:

1 1 1 Pre Bid Conference JGB Lobby Level Meeting Room December 12, 2012 9:00 am IFB FQ12210 Rehabilitation of Parking Garages at Vienna (South), Southern and Suitland

2 2 Topics of Discussion General Information Parking Garages Location and Description Vienna (South) Southern Suitland Typical Rehabilitation Requirements Typical Expansion Joint to Be Repaired Typical Construction Joint to Be Repaired Typical Concrete Cracks to Be Repaired Program Schedule Requirements Receipt of Written Questions Site Visit

3 3 General Information The Washington Metropolitan Area Transit Authority (WMATA) Parking Garages at Vienna (South), Southern and Suitland are three active commuter parking garages that serve the Washington DC Metro area stations along the K and F lines. Commuter garages have a high occupancy rate during normal business hours, Monday through Friday. Occupancy rates are much lower during the weekends. Rehabilitation work is expected to be mostly completed during the normal work week.

4 4 Suitland Southern Vienna (South) Parking Garages Location and Description

5 5 Vienna (South) Vienna (South) Parking Garage Located south of Curtis Memorial Parkway (Route 66) at the corner of Vaden Drive and Saintsbury Drive. It serves as public parking for the Washington DC Metro K Line – Vienna / Fairfax – GMU Station. Constructed in 2000. Precast and prestressed elevated structure. Slab on grade at the basement level. 5 Elevated decks. Approximate square footage is 733, 200. Vienna (South) Parking Garage

6 6 Southern Southern Parking Garage Located between Southern Avenue SE and Oxon Run Drive. It serves as public parking for the Washington DC Metro F Line – Southern Avenue Station. Constructed in 1995. Precast and prestressed elevated structure. Slab on grade at the ground level. One elevated deck. Approximate square footage is 580,000.

7 7 Suitland Suitland Parking Garage Located along Silver Hill Road and Suitland Parkway. It serves as public parking for the Washington DC Metro F Line – Suitland Station. Constructed in 1995. Precast and prestressed elevated structure. Slab on grade at the ground level. 2 Elevated decks. Approximate square footage is 600,000. Suitland Parking Garage

8 8 Parking Garages Location and Description Vienna (South) Parking Garage Southern Parking Garage Suitland Parking Garage N

9 9 Typical Rehabilitation Requirements The rehabilitation of all three parking garages consists (but not limited to) of the following: Waterproofing of all elevated decks. Replacement of expansion and construction joints. Repair of concrete spalls at top and underside of decks. Repair of concrete cracks at top and underside of decks. Replacement of bearing pads at underside of precast members. Replacement of deck drainage system. Cleaning and painting of fire lines and wash down piping. Removal and new application of striping at all parking levels. Renovation of stairwells and bathrooms. Replacement or cleaning of electrical conduits and components.

10 10 Typical Expansion Joint to Be Repaired Vienna (South) Parking Garage Southern Parking Garage Suitland Parking Garage

11 11 Typical Construction Joint to Be Repaired Vienna (South) Parking Garage Southern Parking Garage Suitland Parking Garage

12 12 Typical Concrete Cracks to Be Repaired Vienna (South) Parking Garage Southern Parking Garage Suitland Parking Garage

13 13 Program Schedule Requirements Duration – X calendar days from Notice to Proceed (including submittals, fabrication, delivery, construction & testing). Bar charts are required in Primavera Software (P6 or Compatible)

14 14 Receipt of Written Questions Remarks and explanations given in response to questions in this meeting shall not modify the terms of the solicitation, unless a written amendment is issued by the Authority. The Authority will send answers to questions received and distribute to bidders. The Authority will issue an amendment as required. QUESTIONS ?

15 15 Site Visit For Vienna (South) parking garage: When: Wednesday, December 12, 2012, from 1 P.M. to 3 P.M. Where: 9550 Saintsbury Dr., Fairfax, VA 22031 For Southern parking garage: When: Thursday, December 13, 2012, from 1 P.M. to 3 P.M. Where: 1411 Southern Avenue, Temple Hills, MD 20748 For Suitland parking garage: When: Thursday, December 13, 2012, from 9 A.M. to 11 A.M. Where: 4500 Silver Hill Rd., Suitland, MD 20746


Download ppt "1 1 Pre Bid Conference JGB Lobby Level Meeting Room December 12, 2012 9:00 am IFB FQ12210 Rehabilitation of Parking Garages at Vienna (South), Southern."