Presentation is loading. Please wait.

Presentation is loading. Please wait.

Mount Vernon Yacht Club Long Range Projects. Projects under consideration Replace/repair bulkhead along parking lot Dredging Replace/Upgrade of C and.

Similar presentations


Presentation on theme: "Mount Vernon Yacht Club Long Range Projects. Projects under consideration Replace/repair bulkhead along parking lot Dredging Replace/Upgrade of C and."— Presentation transcript:

1 Mount Vernon Yacht Club Long Range Projects

2 Projects under consideration Replace/repair bulkhead along parking lot Dredging Replace/Upgrade of C and D Docks – Include upgrade of electric for E Dock Resurface parking lot, driveway

3 Bulkhead -- 450 Linear Feet

4 Bulkhead – Possible Soil Loss

5

6

7 Bulkhead – Sheeting Old, deteriorating sheeting – 25+ years old – 2x10 – Rotting?

8 Bulkhead – Sheeting

9

10

11

12

13 Bulkhead Replace or Repair Two experts recommend replacing entire bulkhead – Cost estimates range from $400/ LF and up – There are 450 linear feet of bulkhead ($180k) – Permitting could get extensive and expensive Three experts recommend replacing only the sheeting – Replace all sheeting with 3x10 boards ($90k) – Piles, whalers (Cross timbers) and tie rods are in good shape – Permitting should be simple – do job gradually as a repair MVYC expert (Ricky) recommends replacing only the bad sheeting – Do it as normal maintenance – no permitting – In-house project, a few hundred dollars at a time – We will investigate these options over the summer

14 Bulkhead Replace or Repair PROJECTCOSTALTERNATE APPROACHESCOST Bulkhead replacement180,000Bulkhead sheeting only90,000 Engineering & permits5,000 Engineering & permits0 Total185,000Total90,000

15 Dredging Need to establish maintenance level for future dredging Need to start permit process now – 6 months to 1 year to obtain permit – Permit process will be more difficult from 2013 on – Economical disposal of spoils until end of 2012 Dont think VMRC will exercise jurisdiction over man- made boat basin Army Corps of Engineers approval may be uncomplicated Fairfax County permit process is unknown Team has been organized to apply for permit

16 Dry Marina – January 2006

17

18 Dredging – Estimated Costs Dredging200,000 Engineering/ permit fees 10,000 Total210,000

19 C & D Docks + Electrical for E Dock

20 C Dock

21 Finger Pier – C Dock

22 C Dock Electrical Service

23 D Dock

24 E Dock

25 New Pedestals for C, D and E Docks Provide electrical and water service

26 C Dock Layout

27 D Dock Layout

28 C & D Docks + Electrical for E Dock Considerations: Complete replacement of C&D a significant outlay ($186k) Need longer fingers plus more piles to accommodate medium- sized boats on south side of C Dock Main decking 6 years old – At a minimum finger piers need replacing on both docks Need updated electrical and plumbing – Add pedestals for C Dock (8), D Dock (1), E Dock (4) – Install new Dominion Power 200 amp panel for C and D docks – Install electrical service from new panel to C and D Docks Feed E Dock from house panel – Connect pedestals to electric and water sources Could be a lengthy permit process

29 C & D Docks plus E Dock Electrical C & D Dock ReplacementC & D Dock Upgrade Remove and dispose existing * 5,000 Remove and dispose existing 1,000 Docks and piles installed 115,000 Finger piers @ 20/SF 14,500 Piles 12 @ $450** 5,400 Electrical installation 24,000 Electrical installation 24,000 Electrical Hook up & Water install 5,000 Electrical Hook up & Water install 5,000 Pedestals: 12 dual, one single 9,000 Pedestals: 12 dual, one single** 9,000 Engineering/permit fees 4,000 Electrical permit fees 0 Total 162,000 Total 58,900 Contingency @ 15% 24,300 Contingency @ 20% 11,780 Total C & D Dock 186,30070,680 * 2005 cost for A & B Docks $32,500 ** Could be fewer piles and pedestals PROJECTCOSTALTERNATE APPROACHESCOST

30 Parking Lot/Driveway resurfacing Should be done, but only after heavy equipment work is finished on site – Dredging – Bulkhead work – Material delivery for C & D

31 Parking Lot/Driveway resurfacing

32

33

34 Driveway-Repair, repave75,000

35 Project Capital Cost Summary Min Max Bulkhead – repair/replacement $ 0 - $ 90,000 $185,000 Dredging 210,000 210,000 C & D Dock repair/replace 71,000 186,000 Parking lot resurfacing 75,000 75,000 Totals $356,000 - $446,000 $656,000

36 Recommended sequence Depends on approaches, but in general: 1.Beging Dredging effort – Apply for dredging permit now – Permit process will be more difficult from 2013 on – There is a time constraint on economics of spoils disposal (end of 2012 calendar year) 2.Bulkhead repair/replace – investigate extent of problem 3.C & D Dock repair/replace, + electrical service for E Dock – Set panel and run new electric service for C, D and E Docks (Could be done at any time) 4.Resurface parking lot after all heavy equipment work for dredging, bulkhead and dock work is finished

37


Download ppt "Mount Vernon Yacht Club Long Range Projects. Projects under consideration Replace/repair bulkhead along parking lot Dredging Replace/Upgrade of C and."

Similar presentations


Ads by Google