Mount Vernon Yacht Club Long Range Projects
2
Projects under consideration Replace/repair bulkhead along parking lot Dredging Replace/Upgrade of C and D Docks – Include upgrade of electric for E Dock Resurface parking lot, driveway
3
Bulkhead -- 450 Linear Feet
4
Bulkhead – Possible Soil Loss
7
Bulkhead – Sheeting Old, deteriorating sheeting – 25+ years old – 2x10 – Rotting?
8
Bulkhead – Sheeting
13
Bulkhead Replace or Repair Two experts recommend replacing entire bulkhead – Cost estimates range from $400/ LF and up – There are 450 linear feet of bulkhead ($180k) – Permitting could get extensive and expensive Three experts recommend replacing only the sheeting – Replace all sheeting with 3x10 boards ($90k) – Piles, whalers (Cross timbers) and tie rods are in good shape – Permitting should be simple – do job gradually as a repair MVYC expert (Ricky) recommends replacing only the bad sheeting – Do it as normal maintenance – no permitting – In-house project, a few hundred dollars at a time – We will investigate these options over the summer
14
Bulkhead Replace or Repair PROJECTCOSTALTERNATE APPROACHESCOST Bulkhead replacement180,000Bulkhead sheeting only90,000 Engineering & permits5,000 Engineering & permits0 Total185,000Total90,000
15
Dredging Need to establish maintenance level for future dredging Need to start permit process now – 6 months to 1 year to obtain permit – Permit process will be more difficult from 2013 on – Economical disposal of spoils until end of 2012 Dont think VMRC will exercise jurisdiction over man- made boat basin Army Corps of Engineers approval may be uncomplicated Fairfax County permit process is unknown Team has been organized to apply for permit
16
Dry Marina – January 2006
18
Dredging – Estimated Costs Dredging200,000 Engineering/ permit fees 10,000 Total210,000
19
C & D Docks + Electrical for E Dock
20
C Dock
21
Finger Pier – C Dock
22
C Dock Electrical Service
23
D Dock
24
E Dock
25
New Pedestals for C, D and E Docks Provide electrical and water service
26
C Dock Layout
27
D Dock Layout
28
C & D Docks + Electrical for E Dock Considerations: Complete replacement of C&D a significant outlay ($186k) Need longer fingers plus more piles to accommodate medium- sized boats on south side of C Dock Main decking 6 years old – At a minimum finger piers need replacing on both docks Need updated electrical and plumbing – Add pedestals for C Dock (8), D Dock (1), E Dock (4) – Install new Dominion Power 200 amp panel for C and D docks – Install electrical service from new panel to C and D Docks Feed E Dock from house panel – Connect pedestals to electric and water sources Could be a lengthy permit process
29
C & D Docks plus E Dock Electrical C & D Dock ReplacementC & D Dock Upgrade Remove and dispose existing * 5,000 Remove and dispose existing 1,000 Docks and piles installed 115,000 Finger piers @ 20/SF 14,500 Piles 12 @ $450** 5,400 Electrical installation 24,000 Electrical installation 24,000 Electrical Hook up & Water install 5,000 Electrical Hook up & Water install 5,000 Pedestals: 12 dual, one single 9,000 Pedestals: 12 dual, one single** 9,000 Engineering/permit fees 4,000 Electrical permit fees 0 Total 162,000 Total 58,900 Contingency @ 15% 24,300 Contingency @ 20% 11,780 Total C & D Dock 186,30070,680 * 2005 cost for A & B Docks $32,500 ** Could be fewer piles and pedestals PROJECTCOSTALTERNATE APPROACHESCOST
30
Parking Lot/Driveway resurfacing Should be done, but only after heavy equipment work is finished on site – Dredging – Bulkhead work – Material delivery for C & D
31
Parking Lot/Driveway resurfacing
34
Driveway-Repair, repave75,000
35
Project Capital Cost Summary Min Max Bulkhead – repair/replacement $ 0 - $ 90,000 $185,000 Dredging 210,000 210,000 C & D Dock repair/replace 71,000 186,000 Parking lot resurfacing 75,000 75,000 Totals $356,000 - $446,000 $656,000
36
Recommended sequence Depends on approaches, but in general: 1.Beging Dredging effort – Apply for dredging permit now – Permit process will be more difficult from 2013 on – There is a time constraint on economics of spoils disposal (end of 2012 calendar year) 2.Bulkhead repair/replace – investigate extent of problem 3.C & D Dock repair/replace, + electrical service for E Dock – Set panel and run new electric service for C, D and E Docks (Could be done at any time) 4.Resurface parking lot after all heavy equipment work for dredging, bulkhead and dock work is finished