Workforce / Students / Tasks
What tasks urgently need workforce? What workforce is available? Looking for tasks?
2
Expected workforce availability from outside JLab for installation,
testing, calibration 8 months before experiment (person-months) Faculty 47 Postdoc Graduate students 64.5 Technician 5 undergrad 14 Total Expected workforce availability for running shifts (if over 3 months) Faculty 13 Postdoc 9.2 Graduate students 29 undergrad 1 Total
3
~8 months installation/callibration/tesing
~3 months running faculty postdoc grad stu undergrad tech. other Argonne S. Riordan 0.7 1.3 Cal. State L.A. K. Aniol 3 6 CMU B. Quinn 4 8 Christopher Newport P. Monaghan 5.5 11.5 Glasgow J. Annand 1 0.5 Hampton M. Kohl 0.8 Idaho State M. Khandaker ? INFN/ari S. Marrone INFN/Catania V. Belini 2 INFN/Genoa P. Musico INFN/Rome E. Cisbani Norfolk State V. Punjabi NC A&T A. Ahmicouch 7 NC Central C. Jackson 1.75 0.75 James Madison G. Niculescu JLab B. Wojtsekhowski N/A U. Conn. A. Puckett U.Va. G. Cates " N. Liyanage 16 William & Mary T. Averett 1.5 Rutgers R. Gilman St. Mary's A. Sarty Stony Brook K. Kumar Yerevan A. Shahinyan 12 53 22.8 64.5 19.5 5 24.45 9.2 29 total 164.8 63.65
4
~8 months installation/callibration/tesing
contact faculty postdoc grad stu undergrad tech. other total GEM U.Va. N. Liyanage 8 16 24 INFN/Rome E. Cisbani 1 0.5 2.5 INFN/Catania V. Belini 4 2 9 Hampton M. Kohl 0.8 3 11.8 47.3 HCAL CMU B. Quinn 6 25 U. Conn. A. Puckett Rutgers R. Gilman 0.75 1.5 3.25 36.25 GRINCH William & Mary T. Averett 14 NC A&T A. Ahmicouch 7 12 James Madison G. Niculescu Stony Brook K. Kumar Yerevan A. Shahinyan 53 BB Hodo Glasgow J. Annand Cal. State L.A. K. Aniol CDET Christopher Newport P. Monaghan 5.5 11.5 St. Mary's A. Sarty 17.5 BB Hall A postdoc Flexible Argonne S. Riordan 0.7 1.3 NC Central C. Jackson 1.75 2.75 4.75
5
BigBite (D.H.) could really use students to help with cable testing, re-cabling as well as DAQ testing. Who’s available???? HCal Fall 2017 / Spring 2018 Sub-assembly #1 cosmic commissioning [CMU] JLab PMT base assembly (need ~100) [CMU] (installation) Summer/Fall 2018 Continue cabling and tests Install pulser distribution What other ongoing tasks need workforce (at JLab) to have systems ready for installation Dec (and prepare in advance for final cabling etc.) ??
7
Milestones Needed **SOON** for all systems (detectors, software, DAQ, …) for reply to ERR recommendations. Milestones before end of next year, with dates, indicating readiness to begin installation in hall. To: (before Monday!)