Presentation is loading. Please wait.

Presentation is loading. Please wait.

GERAN update on ER-GSM band

Similar presentations


Presentation on theme: "GERAN update on ER-GSM band"— Presentation transcript:

1 GERAN update on ER-GSM band 11. 04. 2013
UIC RF WS GERAN update on ER-GSM band

2 Introduction Standardisation work progressing to include ER-GSM band into relevant Standards ETSI TC RT activities closed 3GPP GERAN activities ongoing... ...ETSI MSG activities pending 873 918 876 921 880 925 890 935 P-GSM E-GSM R-GSM ER-GSM 915 960 UL DL

3 Frequency ecosystem in the Standards
3GPP 1st step ETSI TC RT GSM railway TSG GERAN GSM GPRS EDGE EN defining R-GSM band Change Request needed to refer to ER-GSM band New version of TS mentioning ER-GSM band TS TS (RF parameters) TS TS (conformance testing) MSG European Harmonized Standards EN defining R-GSM band TSG CT CN Function (VGCS, billing) TS (signalling capabilities) Harmonized Standard = applicable at EU level 2 phases approach: need to update 3GPP TS first

4 3GPP GERAN activities 1/2 During 3GPP GERAN # 57 a Liaison Statement from 3GPP RAN4 was received Reminder: RAN4 is responsible for UTRA/E-UTRA specifications (UMTS and LTE experts) The LS answers the GERAN question on UMTS and LTE BS sensitivity and blocking performances not explicitly defined in RAN4 specifications  RAN4 recommends to set mitigation techniques (e.g. power reduction), so that Minimum Coupling Loss of 104/106 dB is ensured between ER-GSM BTS emission and UTRA/E-UTRA reception Based on this answer NSN proposed a further proceeding No question about RAN4 assumptions, but a segmentation approach of the ER-GSM band into different sub- bands, with power levels for each sub-band left to be defined in the co-existence study  Mechanism allowing to minimize the power reduction required by RAN4 (see slide 6) Kapsch CarrierCom disagreed with the conclusions from RAN4 Assumptions on sensitivity of UTRA/E-UTRA equipments seem to be under evaluated, estimated blocking requirements at 918 MHz very conservative  Critics rejected as RAN4 recommendations on their specifications prevail Limitations of the emissions of ER-GSM equipments should be subject to regulatory rules and not 3GPP specifications  Public operators and Industry firmly in favour of a mandatory requirement in TS

5 3GPP GERAN activities 2/2 Kapsch CarrierCom presented 4 contributions
Update of the co-existence analysis  further parameters refined to take into consideration inputs from Public Industry and RAN4 Set of Change Requests to include ER-GSM in GERAN specifications TS , and (see slide 3) TR "RF scenarios"  Proposal to have no mandatory requirement in the main specifications and informative part in the TR Proposal was discarded by Public operators and Industry and they would prefer to have a direct reference to the obligation of non-impact of ER-GSM equipments in the main specifications Offline discussion was held where Kapsch CarrierCom proposed a way forward See next slides for details Generally Public operators and Industry ok with it Way forward not officially communicated, waiting for Railway Operators opinion

6 Simulation of impact: NSN proposal
In their Proposed Further Proceeding NSN Retained ER-GSM BTS power level of 6/8 dB for coexistence with UTRA/E-UTRA from RAN4 assumptions Highlighted that power level at MHz can be up to dBm without restriction Proposed segmentation of ER-GSM band to allow for different carrier output power levels depending on the frequency offset to the GSM 900 UL band Assuming the 40 dB are equally distributed on 3 segments of 1MHz each power limits would be Power limit C ( MHz) = 6/8 dBm  coverage distance divided by 8 Power limit B ( MHz) = 19/21 dBm coverage distance divided by 4-5 Power limit A ( MHz) = 32/34 dBm  coverage distance divided by 2-3

7 Offline session: proposed way forward
Participants and goal Kapsch CarrierCom, NSN, Ericsson, Telecom Italia, Vodafone Attempt to find a compromise solution based on all comments expressed during the official ER-GSM session Main result: it is proposed to add the following paragraph in TS

8 Analysis of the proposed way forward 1/2
Preliminary remarks The proposed way forward is a drastic change from RAN4 and NSN proposals: No limitation of emission power at ER-GSM BTS side Instead it considers emission levels received at victim system In practice the proposed way forward is not directly binding ER-GSM emission, but will require analysis from a regulatory body to assess if victim system is indeed receiving exceeding levels Would a regulator require ER-GSM BTS to minimize the levels at victim side this could be done either by power reduction or engineering modification (antenna gain, tilt, ...) Explanations about figures in the proposed way forward Reappraisal of RAN4 inputs would lead to considerable delays with jeopardized success Values of -40.4, and dBm and slope of 13 dB/MHz are taken from Kapsch CarrierCom co-existence study on ER-GSM introduction (including RAN4 inputs)

9 Analysis of the proposed way forward 2/2
Graphic representation of the proposed way forward

10 Simulation of impact Goal and Working assumptions
The following analysis derives the worst case scenarios (e.g. 104/106 dB of MCL as assumed by RAN4) to simulate the distance at which a ER-GSM BTS should be placed from a victim system to ensure safe operation of UTRA/E-UTRA equipments  Kapsch CarrierCom is of the opinion that MCL is over estimated and that real cases interferences are likely to be lower than in the simulations The following working assumptions are taken ER-GSM BTS: output RF power = 45 dBm, antenna gain = 17 dB, no tilt, coupling losses = 5dB Victim system: antenna gain = 13 dB, cable losses = 3 dB, tilt effect = 4 dB 3 aiming configuration considered: 0 dB (ER-GSM antenna pointing directly to UMTS site), -3 dB (30° from UMTS site direction), -10 dB (60° from UMTS site direction) Propagation models: Free space model (only valid for distance < 5 km), Hata Urban & Sub-Urban (valid for distance > 1 km)

11 Simulation of impact: victim considered = MCBTS

12 Simulation of impact: victim considered = UTRA

13 Simulation of impact: victim considered = E-UTRA

14 Conclusions Pros of the way forward Cons of the way forward
Balance power at 3GPP GERAN level not in favour of the railways Inductive limitation (received signals at victim system): implication of regulatory bodies Different methods to implement mitigation if required Limited impact on deployment scenarios provided RAN4 assumptions are unrealistic Fastest way to finalize ER-GSM band introduction in 3GPP GERAN specifications Cons of the way forward Some channels will not be available in dense urban areas Could jeopardize deployment scenarios of ER-GSM sites even years after  unless a precedence rule is established stating that the way forward is not applicable to UMTS/LTE sites activated after ER-GSM BTS deployment

15 Next steps RTEGSM-R #14 meeting on 23-24 April in Munich
Drafting of Change Requests / Liaison Statement towards 3GPP GERAN 3GPP GERAN #58 meeting on May in Xiamen Continued discussion on impact from ER-GSM band introduction onto existing systems Approval of Change Requests?

16 Thank you for your attention.
Thomas Chatelet Railways Regulatory Affairs Railways Customer Solutions Management Kapsch CarrierCom France SAS SITE DE IMMONTIGNY | 1 RUE JEAN PIERRE TIMBAUD | CS | SAINT QUENTIN EN YVELINES CEDEX Phone +33 (0) | Mobile +33 (0) | Please Note: The content of this presentation is the intellectual property of Kapsch AG and all rights are reserved with respect to the copying, reproduction, alteration, utilization, disclosure or transfer of such content to third parties. The foregoing is strictly prohibited without the prior written authorization of Kapsch TrafficCom AG. Product and company names may be registered brand names or protected trademarks of third parties and are only used herein for the sake of clarification and to the advantage of the respective legal owner without the intention of infringing proprietary rights.

17


Download ppt "GERAN update on ER-GSM band"

Similar presentations


Ads by Google