Burton Elementary School
876 Glenwood Avenue Group 8: David Boley, Deneb Bosch, Nathen Miller, Thanh-An Sam
2
Scope 450 students 900 SF. / 25 students per OSFC code for academic use 67, 950 SF. max: but shall be greater than 52, 850 SF Not to exceed $160.23/SF. for construction Not to exceed $185.88/SF. total funding
3
Budget Total SF 63,529 For Construction
63,529 x $ = $10,176,251.67 Total cost 63,529 x $ = $11,808,770.52
4
Milestone Schedule Milestone Schedule One Year Fall 09' Winter 09'
Spring 10' Summer 10' Activity Duration (Weeks) Excavation/Foundation 8 Structure 12 Exterior Skin/Close-In 10 Fitout/MEP Demo existing 4 Relocate equipment 1 Grading/Parking Installation 7 Construction float 6
5
Project Goals & Performance
Maximum Response Minimum Response *Safety/ Security of students and workers Image/ performance User comfort Flexibility/ expandability of building Energy/ O& M cost effectiveness Capital cost effectiveness Schedule Site planning/ image Operational Effectiveness Community values Environmental/ Locality
6
Fast Diagram
7
Functional Analysis Subsystems Functions Cost Comments: Class Rooms
Educate Students $5,576,004.00 Could save money through design simplification Admin/Security Area Guarantee Safety/Security $640,920.00 Final price should be lower due to simple design Fire Protection Meet Codes $203,585.00 Lower cost through Competetive bidding Mechanical System $2,035,850.00 Electrical System $1,017,925.00 Plumbing $508,962.00 Cafeteria/Auditorium $765,899.00 Could lower cost by removing Auditoriun Stage Gym/Music Room $2,002,875.00 High Cost may not be needed
8
Review of Project Relocate the placement of the building
Orient classroom wing to allow easier access to other functions of the building. Eliminate unnecessary curves and angles.