1 INGONYAMA TRUST BOARD’S 2ND AND 3RD QUARTER PERFORMANCE AND FINANCIAL REPORT: 2015 – 2016 FINANCIAL YEAR PRESENTATION TO THE PORTFOLIO COMMITTEE ON RURAL DEVELOPMENT AND LAND REFORM DATE : 17 FEBRUARY 2016 2019/05/07

2 CONTENTS Introduction Overall Programme Performance
Programme 1 : Administration Programme 2 : Land Management Programme 3 : Rural Development Programme 4 : Traditional Council Support Overall Financial Performance Educational Awards Accounting Authority meetings Conclusion 2019/05/07

3 INTRODUCTION The presentation covers the organisational programme performance in line with the four (4) programmes of the Ingonyama Trust Board Performance recorded during the period under review is compared against targets set in the 2015 – 2016 Annual Performance Plan (APP) 2019/05/07

4 PROGRAMME PERFORMANCE
2019/05/07

5 PROGRAMME 1 : ADMINISTRATION
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action To ensure that efficient internal resource management is aligned to legislative requirements Number of policies approved by the Board 5 1 No Variance Not applicable Percentage of all moveable assets to be recorded in the asset register 100% 90% Balance of the tractors purchased still in storage awaiting distribution Plan in place to visit storage facility in order to record tractors Percentage of vacant positions to be filled 100% (3) 88.8% 66.6% - 2nd Quarter focus was of filling the position of Head of Secretariat in July 2015; - Positions finalised in 3rd Quarter for Deputy Manager Administration and Assistant Registry Clerk - 2nd Quarter priority was the filling of the (3) vacant posts which were finalised in 3rd Quarter for Deputy Manager Administration, Assistant Registry Clerk. HOD Real Estate position interviews held awaiting finalisation in 4th Quarter. 2019/05/07

6 PROGRAMME 1 : ADMINISTRATION (contd)
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action To ensure that efficient internal resource management is aligned to legislative requirements Percentage of performance agreements signed 100% 94.4% 56 out of 57 Employees signed Performance Agreements during the 2nd Quarter and the balance was to be finalised during 3rd Quarter 1 Employee finalised their performance agreements during the 3rd Quarter Monthly Backup of exchange / file server properly completed 12 3 No Variance Not Applicable Bi annual check of software compliance conducted 2 1 Not applicable Provision of skills development to employees to improve service delivery Number of training programmes conducted 10 Priority during the 2nd Quarter was given to Performance Agreements and Personal Development Plans Revised plan being finalised based on current challenges on the ground 2019/05/07

7 PROGRAMME 1 : ADMINISTRATION (contd)
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action To improve customer relationship Payment of valid invoices paid within 30 days of receipt in finance 100% No Variance Not Applicable Communicati on Strategy approved 1 Not applicable Number of Memorandum of Agreements with Traditional Councils(TC’s) approved 4 - During the 2nd Quarter the translation of the MOU was completed and a plan for engagement of amaKhosi developed; - During the 3rd Quarter the Engagement with Amakhosi was done and two TCs indicated their willingness to sign which are Qiko and Bhidla TCs; - Qiko TC has signed and Bhidla TC is still outstanding Follow up to be done with Bhidla TC for the signed MOU Number of monthly communicatio n reports approved by the Board 12 3 2019/05/07

8 PROGRAMME 2 : LAND MANAGEMENT
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action Provision of secured tenure rights to facilitate development on Ingonyama Trust land Number of land tenure rights approved by the Board 1300 325 106 49 - During the 2nd Quarter there were 2 meetings held in which 162 tenure applications were approved and 106 applications signed by both parties - During the 3rd Quarter there was a requirement of informed consent on residential leases - Also in the 3rd Quarter the reviews of rentals charged on commercial and agricultural leases were done - To Engage and educate the communities on residential leases for informed consent - Finalisation of the rental policy and development of a replacement tool for the residential leases To maintain an intergrated and comprehensive land tenure administration system (database of tenure rights) Quarterly update of land holdings register 4 1 No Variance Not applicable 2019/05/07

9 PROGRAMME 2 : LAND MANAGEMENT (contd)
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action Making Trust land available for infrastructure development Number of MOUs and planning and development agreements approved by the Board 4 1 - During the 2nd Quarter a Draft MOU was developed between the ITB and Newcastle Local Municipality feedback was not received - Follow up with Newcastle Local Municipality - Finalisation of the report by consultants to enable MOU negotiation Prevention and monitoring of illegal occupation of Trust land Number of legal interventions undertaken by the Board 3 - During the 2nd Quarter three areas were threatened with by the illegal occupation of land which as Mathonzi, Gezinsila and Fynn - A letter of demand was sent to the illegal occupier under the Macambini TC Not applicable 2019/05/07

10 PROGRAMME 3 : RURAL DEVELOPMENT
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action Provide support to beneficiary communities to improve food security Number of agricultural projects approved by the Board 5 1 4 - During the 2nd Quarter there were four (4) agricultural projects which were implemented - These projects were carried over to the 3rd Quarter Not applicable To facilitate economic development (industry and rural enterprise establishment) Develop a strategy on economic development Terms of reference drafted prioritised for implementation in 4th Quarter Number of partnership agreements approved by the Board - During the 2nd Quarter work was in progress on identification of relevant partnerships - During the 3rd Quarter the identified partners had not come on board Secretariat to continue and pursue the potential partners 2019/05/07

11 PROGRAMME 3 : RURAL DEVELOPMENT (contd)
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action To identify strategically located land to be utilised for high impact commercial ventures Number of commercial high impact projects approved by the Board 4 1 3 It was identified that the indicator was incorrectly written. A proposed amendment to the indicator to read as Land with high commercial impact identified and approved by the Board Land has been identified in 3 areas (Newcastle, Nyokeni Precinct, Mpophomeni) and is currently being packaged 2019/05/07

12 PROGRAMME 4 : TRADITIONAL COUNCIL SUPPORT
Strategic Objective Performance Indicator Annual Target 2015/16 2nd Quarter Target 2nd Quarter Results 3rd Quarter Target 3rd Quarter Results Reason for variance Corrective action Provide training to Traditional Communities in skills development and capacity building programs Number of traditional councils trained 45 11 9 - During the 2nd Quarter the training programme was reviewed - During the 3rd Quarter the availability of Traditional Councils was a challenge - The results of the review of the training programme in the 2nd Quarter resulted in the development of a training plan for implementation in the 3rd Quarter - The variance for the training programme to be catered in the 4th Quarter to cover the shortfall in performance Facilitate socio – economic investment to communities living on Trust land Number of educational awards granted 100 25 20 2 - During the 2nd Quarter Tembe TC submitted bursary requests - During the 3rd Quarter only two requests were received by the Board Influx of requests expected to be received during the 4th Quarter as a result of school opening for 2016 academic year 2019/05/07

13 FINANCIAL PERFORMANCE
2019/05/07

14 2nd and 3rd QUARTER EXPENDITURE 2015/2016
EXPENDITURE PER PROGRAMME Item Final Budget 2nd Quarter Spending 3rd Quarter Spending Spending to the end of 3rd Quarter Percentage of Total Budget Spent in the 3rd Quarter Mitigation plan on under expenditure R % ADMINISTRATION 40.00 See Note 1 LAND MANAGEMENT 38.77 See Note 2 RURAL DEVELOPMENT 69.89 See Note 3 TRADITIONAL COUNCIL SUPPORT 23.66 See Note 4 39.90 2019/05/07

15 2nd and 3rd QUARTER EXPENDITURE 2015/2016
EXPENDITURE PER ECONOMIC CLASSIFICATION Item Final Budget 2nd Quarter Spending 3rd Quarter Spending Spending to the end of 3rd Quarter Percentage of Total Budget Spent in the 3rd Quarter R % COMPENSATION OF EMPLOYEES 70.41 GOODS AND SERVICES 38.06 RENT ON LAND - ULUNDI OFFICE 77.79 BUILDING AND OTHER FIXED STRUCTURES - 0.84 MACHINERY, EQUIPMENT & VEHICLES 71.44 SOFTWARE AND INTANGIBLE ASSETS 22.85 39.90 2019/05/07

16 NOTES ON EXPENDITURE The total expenditure for Quarter 2 and Quarter 3 amounted to R10.3m and R10.8m respectively. 39.90% of the total budget was spent to the end of Quarter 3 (including capital expenditure) 70.41% of the total salary budget was utilised up to the end of the 3rd quarter. 38.06% of the total goods and services budget was utilised up to the end of the 3rd quarter. 2019/05/07

17 MITIGATION PLAN Note 1 : Administration
The filling of the vacancies for the Deputy manager administration, Real estate manager, Auxiliary clerk and the Business development specialist will result in further expenditure being incurred in quarter four. In excess of R is committed for the 4th quarter for stakeholder /community engagements. It is also envisaged that funds will be utilised for the development of policies, organizational structure and job grading in the 4th quarter. Further audit costs will be incurred during the finalisation of the year end financial statements. 2019/05/07

18 MITIGATION PLAN (contd)
Note 2 - Land management Funds will be utilised for the the land valuation exercise which is to commence in the 4th quarter Funds are to be utilised on training of traditional councils on land management Note 3 - Rural Development Irrigation systems are to be installed for the agricultural projects. Expenditure is to be incurred for completion of existing projects. Note 4 - Traditional Council Support The Board has appointed a Business development specialist who is working with Traditional Councils to draft business plans for the utilization of funds. The Board has set aside R for bursaries to be paid in terms of the “Funda Zulu Bursary scheme”. 2019/05/07

19 SCHEDULE OF GOODS AND SERVICES
Item 2nd Quarter Actual 3rd Quarter R Legal fees - other Staff Training Land Tenure Information System Advertising and public awareness campaign Bank Charges Cleaning repairs & other expenses Payments to community beneficiaries Tenure Upgrade and finalisation of Settlement - Projects launches and informative meetings Workshop for Co - operation agreement Workshops and road shows HRM Strategy and Communication Strategy Board Members Remuneration 2019/05/07

20 SCHEDULE OF GOODS AND SERVICES (contd)
Item 2nd Quarter Actual 3rd Quarter R Agricultural Projects - Expenses Insurance Motor Vehicle Expenses External Audit Fees Internal Audit Committee Remuneration Internal Audit Fees - Computer Software/Licencing Fee Stationery and Printing Travel , Accommodation, Meetings Electricity and Water Security Expenses Telephone/Data 2019/05/07

21 SCHEDULE OF REVENUE R % Item Actual income for the 2nd Quarter
Actual income for the 3rd Quarter Cumulative to the end of 3rd Quarter Budget for the year Cumulative actual over budget percentage R % RENTAL INCOME R 4,671,235 R 2,976,129 R 21,574,980 R 17,642,621 122,29% SERVITUDES,REFUND ON LEGAL FEES AND OTHER R ,404 R R 1 ,006,636 R ,650 285,45% INVESTMENT INCOME R 2,875,916 R 2,990,544 R 8,702,956 R 10,647,248 81,74% TOTAL INCOME EXCLUDING RESERVES AND TRANSFER PAYMENT R 7,633,555 R 6, R 31,284,572 R 28,642,519 109,22% TRANSFER PAYMENT R 5,721,000 R 5,050,000 R 16,887,000 R 18,069,000 93,46% RESERVES - R 40,930,905 00,00% TOTAL INCOME R 13,354,555 R 11, R 48, R 87,642,424 54,96% 2019/05/07

22 NOTES ON 2nd and 3rd QUARTER INCOME
The total revenue generated for quarter 2 amounted to R7.6 million and for quarter 3 amounted to R6.7 million (excluding transfer payments). The accumulative income at the end of quarter 3 amounted to R31.2 million which exceeded the budget by 9.22%. 93.46% of the transfer payment was received up to the end of quarter 3. 2019/05/07

23 EDUCATIONAL AWARDS – Granted 2nd QUARTER
Total Amount : R No of Males No of Females Total 11 9 20 Name of Student Gender Field NZ Thusi Female Bachelor of Public Admin University of Zululand SM Banda Male B.Com Business Management & Economics M Ndlazi SS Manzini B.Com Accounting NB Manzini Bachelor of Communication Science TN Zwane Bachelor of Education MM Khumalo SN Mahlangu Nursing KC Gumede L Mthembu N Thwala Science Foundation SN Gwala Bachelor of Law T Ngema Bachelor of Arts DM Shange LS Msweli SS Mageba Z Mkhumbuzi B.Com Banking NV Gumede KK Mathenjwa ML Mdluli 2019/05/07

24 EDUCATIONAL AWARDS – Granted 3rd QUARTER
Total Amount Paid : R No of Males No of Females Total 2 Name of Student Gender Field Institution Amount L Ntanzi Female Bachelor of Education University of Zululand LH Thango Bachelor of Law 2019/05/07

25 ACCOUNTING AUTHORITY MEETINGS
MEETING TYPE/QUARTER EXECUTIVE COMMITTEE (EXCO) TENURE COMMITTEE BOARD QUARTER 2 22 July 30 July 14 August 18 September 13 August 25 August 25 September 29 September QUARTER 3 21 October 23 October 30 October 09 December 27 November 20 November 30 November 14 December 11 December 21 December 2019/05/07