Problem: Bridges do not achieve nominal form height. What is the root cause? Answer: unknown- not enough information Material related issues Process or machine related issues Tooling related issues
3
Case Study: Lance and Form Bridge (Form Height)
Material Related Issues: Material can only stretch so far. Material thickness thinner or thicker than what the tool was designed for. Material choice impacts springback Plastic coatings have a thickness.
4
Case Study: Lance and Form Bridge (Form Height)
Process or Machine Related Programmed depth Shims installed in die holder Repeatability of stroke control Running on a different machine Tonnage limits Others..
5
Case Study: Lance and Form Bridge (Form Height)
Tool Related Tool Length Tool wear Tool was sharpened (see red lines)- Upper and lower without sharpening or removing material from ejector. Debris in lower or upper (metal, dirt, plastic coatings) Damaged springs in lower Define nominal height +/- 0.xx mm (Standard tolerance is +/-0.004”(0.1mm) Ejector