Download presentation
Presentation is loading. Please wait.
1
LCLS Undulator System Status and Schedule
Geoff Pile
2
Schedule Considerations
All Argonne girder components are planned to be available at least 1 month before the P3 “Early Start” of Girder Assembly
3
Controls Status and Schedule
Controls – Work Remaining Undulator In-tunnel Rack (UIR) Intra Undulator Cables Electronic Interface Assembly (EIA)
4
Controls Ongoing Work Completed
5
Undulator In-tunnel Rack (UIR)
6
Undulator In-tunnel Rack (UIR)
7
Electronic Interface Assembly (EIA)
~1800 Intra Undulator Cables (pre-made/pre-tested)
8
Undulator Magnets and Supports 1.4.3
Undulators SLAC 7/2007) Support & Motion System - girder, cam movers & fixed supports 3/2008) X translation issue Quads and Correctors 4/2008)
9
Magnets and Supports Ongoing Work Completed
10
All 40 undulators were completed by July 2007
11
Girders Assembled and Packed at Hi-Tech
Girder Manufacture at Metalex Critical Engineering and QA Oversight by Argonne
12
X Translation stop points
13
Tuning block modification
14
37 magnets and 2 sets of spare coils completed 4/08
Quads and Correctors 37 magnets and 2 sets of spare coils completed 4/08
15
Vacuum Systems 1.4.4 46 Vacuum Chambers produced
Manufacture started September 2007 & ended May 2008 33 required 7 spares 1 LTT 5 sacrificed for surface finish measurements Monumental task, huge effort, successful ending. Interest has already been expressed in this technology by other projects around the world.
16
Vacuum
17
Inspection and correction of the LCLS VC end flange perpendicularity
Inspection of the total length of the LCLS Vacuum Chamber Inspection and correction of the LCLS VC end flange perpendicularity
18
Surface Finish Data of 46 Chambers… 33 required (7 spare – 5 sacrificed – 1 LTT)
Extrusion # h (mm) rms transverse slope (mrad) rms longitudinal slope (mrad) 1 353.57 45.45 17.36 2 216.02 20.03 7.98 3 248.52 27.78 8.53 4 236.10 23.69 12.29 5 261.25 23.03 9.47 6 271.06 37.19 13.52 8 302.81 32.23 14.06 9 251.17 31.14 19.12 11 230.72 25.14 9.82 12 294.41 27.43 15.57 13 308.75 26.59 12.64 14 350.85 38.58 19.37 15 306.37 34.49 15.04 17 324.34 26.67 16.20 18 341.19 50.46 20.50 19 246.35 24.78 11.62 20 244.29 18.58 8.08 21 331.53 34.12 15.48 22 268.19 36.40 14.26 23 275.33 40.43 18.56 24 229.15 23.36 10.83 25 258.43 28.51 10.14 26 325.92 46.87 18.46 27 327.66 53.97 23.10 29 327.50 38.76 20.36 30 317.95 45.59 18.91 31 334.76 47.89 19.96 32 230.19 25.44 12.65 33 230.15 21.74 10.27 34 294.70 44.42 16.32 36 245.60 23.85 8.93 37 198.97 17.83 6.85 38 345.21 48.72 22.86 39 311.58 51.02 18.62 40 311.04 35.81 15.33 41 341.13 49.27 15.58 42 233.57 22.24 10.99 43 342.60 56.25 44 321.34 52.82 18.67 45 332.56 19.04 46 254.38 29.50 10.34 Totals (rms) 36.94 15.52 Transverse: The transverse rms slope tolerance is 60 mrad Longitudinal: Slope Criteria from H-D Nuhn adjusted for the oval shape Desirable Acceptable Not Desirable Should Avoid
19
Diagnostic Systems 1.4.5 BPM – BFW – BLM –
20
Diagnostics - BPM
21
BPM Testing at Argonne
22
Beam Position Monitor Large effort- solved serious production problems
Many brazing issues (differential thermal expansion) Window QA problems Multi-step Process now understood 8 now delivered to SLAC -remainder on track Promising World Class Diagnostic
23
1.4.5 - Diagnostics – BFW & BLM
24
Beam Finder Wire All production problems are resolved at this point, but we were somewhat delayed due to issues with repeatability, chamber coating, and electronic modules. Two units that should have shipped last week are on the way to SLAC at this time. Details in Dean Walters’ talk
25
Beam Loss Monitor Five production BLMs will be used to protect the undulators by inhibiting beam bunches following an “above-threshold” radiation event. A joint R&D effort is aimed at enhancing these 5 units to enable LCLS to track each undulator’s accumulated radiation dose. Undulator protection is the highest priority. The BLM will be integrated into the Machine Protection System (MPS) and requires only limited dynamic range from the detectors. Dose tracking will enable long-term magnet damage to be characterized, but requires a radiation detector with large dynamic range (order of 106) and sophisticated diagnostics hardware and software. 30 production BLMs may be built in FY09 if R&D is successful
26
Beam Loss Monitor BLM in Inserted Position (Can be easily made to track out with Undulator) Interface Module
27
Long Term Test
28
Long Term Test
29
Long Term Test
30
Status and Schedule Undulator System Management and Integration
CPR & Costs to go – Generally in good shape. Some unplanned effort has been required in the last two months to solve problems and meet production schedules. Most spares costs were moved to OPC. Final spares costs will be recalculated using actuals and any required adjustments will be made. Green Sheet System A Web-based, almost real time, method of managing Argonne-APS cross- matrixed effort – (up to 60 staff 18FTE’s/year) ASK System A Web-based method of managing deliveries and technical documentation. A dictionary/index style look-up system.
33
Contingency Assessment on Remaining Work (from Reichanadter’s Talk)
5/3/2019 Contingency Assessment on Remaining Work (from Reichanadter’s Talk) 33 Assessment is a bottoms-up, risk-based estimate of “potential need” by each CAM 33 Test 33
34
Almost all deliveries complete by July 2008!
Summary Almost all deliveries complete by July 2008! Production BLMs? TBD (2009) Argonne Construction team rolls off the project in July Argonne Management team drops to half-time in mid-July, and rolls off the project in September. FY09 – a small budget is included for installation and commissioning support
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.