1 Presenter Tony Bosnich 2014
Planning and Organising Two Planning and programming Matching task to Programme L o D Use title slide layout Presenter Tony Bosnich 2014 © Unitec New Zealand DEPARTMENT OF CONSTRUCTION

2 L o D = Level of detail Outcome
To establish the level of task detail and match it with the Desired programme level detail. L o D = Level of detail

3 Summary of Types of programme
1.Pretender Plan 2.Tender construction Plan 3.Accepted construction Plan (Contractual Programme Realistic accepted by both parties.) Establish form of programme control 4.Target programme 5.Rolling or look ahead three weekly programmes 5a.Sub specialised trade and section programmes 6.Provision for On going monitoring and adjustment of all programmes. Objective is to keep with in realms of Contractual programme to avoid LDs and penalties DEPARTMENT OF CONSTRUCTION

4 Task definition Tasks –an individual item or sub project of work by a single person, trade or organisation , which when combined with other tasks in the correct sequence and relationship will result in an event occurring. Components of Task -Description - Duration -Relationship with other tasks Note - a task achieves nothing in isolation it is only when it is combined with other tasks its purpose becomes clear >>DEPARTMENT TITLE EDIT IN HEADER & FOOTER

5 Exercise Consider the Programmes Types No 1 to 6 Make up a matrix table No Type of programme L o D of task Sample Task name Duration unit What is the governing factor to be considered to be when establishing the L o D.? >>DEPARTMENT TITLE EDIT IN HEADER & FOOTER