Project Organization – getting started
Establish project management team Define technical objectives- requirements, deliverables Define Work Breakdown Structure Define project organization Assign responsibilities for WBS elements Establish reporting relationships/org chart Develop management tools and procedures, including configuration control, cost / scheduling system, CAD system, Web site, etc. Develop conceptual design – (CAD models, dwgs, cost, etc) 11 August, 2005 ITER TBM Meeting
3
Work Breakdown Structure (WBS) provides roadmap for project management
Organizes all the tasks into outline form Establishes the scope of each task, so Responsibilities are clear Bases for cost estimates are clear Easily modified, expanded as more detail becomes available Includes WBS dictionary that expands definition of each element 11 August, 2005 ITER TBM Meeting
4
WBS for US Contributions to ITER built around major procurement packages
WBS 1.0 (Level 1): Total approved US ITER scope WBS 1.X (Level 2): work groups, correlates with ITER WBS) WBS Tokamak (Magnets, Blanket/Shield) WBS Tokamak Ancillary Equipment and Cryostat WBS Tokamak Fluids (Vac Pumping and Fueling) WBS Power Supplies WBS Port Interfacing Systems (IC/EC H&CD, Diagnostics) WBS Project Support WBS Support to International team) WBS 1.X.Y (Level 3): Major systems WBS 1.X.Y.Z (Level 4): Major Procurement Packages (9) WBS 1.X.Y.Z.W (Level 5): Standard elements Administration R&D Engineering (design, Title III) Fabrication/Procurement Installation 11 August, 2005 ITER TBM Meeting
5
Possible WBS elements for ITER TBM
Each element would include: Administration Engineering (Design and Title III) R&D Materials and subcontracts (procurements) Fabrication and assembly Installation Cost would include: Labor hours, rates M&S (Procurements) Overhead Escalation 11 August, 2005 ITER TBM Meeting
6
Technical Baseline must be under configuration control
General Requirements Document System Requirements Documents System Description Documents Technical specifications Procedures Drawings 11 August, 2005 ITER TBM Meeting
7
Acquisition Strategy: (elements and example schedule for US ITER)
Ref: C. Strawbridge, ITER mtg, Oct. 2004 11 August, 2005 ITER TBM Meeting
8
Everything costs more and takes longer than planned
Summary Project planning and management must be in place from inception of project, must develop Project scope and technical requirements WBS and responsibilities Resource loaded schedule DOE requires rigorous management processes and documentation, projects phased with critical decisions CD-0,1,2,3,4 Everything costs more and takes longer than planned 11 August, 2005 ITER TBM Meeting