ctcLink Project Update ctcLink Steering Committee

Similar presentations


Presentation on theme: "ctcLink Project Update ctcLink Steering Committee"— Presentation transcript:

1 ctcLink Project Update ctcLink Steering Committee
April 23, 2019 Choi Halladay - District Vice President for Administrative Services Pierce College, ctcLink Steering Committee Chair Christy Campbell – SBCTC ctcLink Project Director Rev. 4/22/2019

2 Agenda Item Description Duration Facilitator 1 . Welcome Christy 2.
1 . Welcome Christy 2.  Approval of Minutes 2 Minutes Choi 3.  ctcLink Program Status Remediation (CCS, TCC Updates) Deployment Group 2 (Training, Testing, Deployment) Deployment Group 3 (BPFG. Data Validation) Deployment Group 4 (Initiation) Deployment Group 5 (Early Visits/Reporting)  PM Summit, May 6-7; May 8 for DG5 & DG6 30 Minutes 4. Deployment Group Alignment Decision for Shoreline CC 15 Minutes 5. Revisit CPW Approvals by Governance (HRMC Request) 10 Minutes 6. RFP Updates: Continuing Education (Negotiations, New Requests) OAA (Discuss Approach to complete 20 Minutes Dennis 7.  Moran Update 5 Minutes Paul 8. Action Items Review and Agenda Items for Future Meeting Executive Sponsor Engagement cELC/President Engagement SC Charter – Executive Sponsor Role 8 Minutes Christy/Janelle/Reuth 9.  Meeting Closure

3 Ctclink Minutes – Approval
April 9, 2019

4 Ctclink program status
Remediation (CCS, TCC Updates) Deployment Group 2 (Training, Testing, Deployment) Deployment Group 3 (BPFG, Data Validation) Deployment Group 4 (Initiation) Deployment Group 5 (Early Visits/Reporting) PM Summit: 2 Days - Focused on College Implementation Activities 1/2 Day - Focused on College Initiation Activities

5 Pilot remediation overview & status
Date Total Open Items Open Items With a Plan to Complete (Appendix A) Open Items Needing a Replacement Solution (Appendix A) Open Items That Were Closed, but Reopened in Remediation Agreement (Appendix B) 2016, 2017, 2018 Financial Books Absence Management (DG2) DRS Redistribution (In Testing) Continuing Education Online Admissions Budget Planning Financial Aid Customizations 11/29/17 195 101 10 84 12/13/18 41 29 2 4/01/19 23 11 DRS – Department of Retirement Systems *FirstLink (pilot) colleges are validating open and closed items/numbers

6 ctcLink Remediation Status Reports – April 1 to 12, 2019
Solution Status Due Date Campus Solutions 10 of 45 remain open DG3 Financial Management 5 of 39 remain open DG2 Human Capital Management 6 of 25 remain open Faculty Workload Complete March 2019 DRS Redistribution Preparing for UAT April 2019 Absence Management Security Audit Controls Security Redesign Mapping Framework FLC / DG2 Student Billing/Third-Party Billing April 2019 Budget Planning Form Work Group Jan 2020 Online Admissions App Governance Continuing Education Vendor Negotiations Chart of Accounts Due/Finish Status TCC Chart of Accounts Adoption Kickoff Dec. 12, 2018 Complete CCs Chart of Accounts Adoption Kickoff Feb. 1, 2019 Foundational Chartfield Configuration March 22, 2019 College Configuration Review and Updates May 3, 2019 In Progress Functional and System Integration Testing May 10, 2019 User Acceptance Testing May 10 - June 3, 2019 Not Started Readiness Gate / Go-No Go Decision June 10, 2019 Production Cutover July 2019 Community Colleges of Spokane R Remediation Items progress this period Student Billing – UAT held Wed 4/11. CCS found two issues. Security Audit Controls – In progress. Bank Statement se Accurate Reporting for DRS & PEBB - Ready now for System Integration Testing. New SBCTC ticket created to address DRS redistribution Third-Party billing – Failing System Integration Testing. UAT TBD. FY Close – see previous slides. Book-to-Bank - Cash Reconciliation - Focus now is on reconciling the three cash accounts making up our $18-million variance (same accounts for TCC). SBCTC Project team working on providing reports/workflow of behind the scenes ctcLink processing of the transactions going into these accounts. Can’t close FY 16,17,18 without reconciling cash accounts. *If status is yellow or red, describe why. Absence management passed UAT, but CCS validating some calculations. Student Billing UAT complete, CCS had a couple issues. Third-Party Billing & DRS pending UATs. Unable to close FY16, 17 & 18 until cash reconciliation is completed. 39 open remediation tickets. Tacoma Community College G Remediation Items progress this period See SBCTC status update for Remediation items, tickets, and worklist. Planned for next period Receive detail for open and closed remediation tickets from Christy and team. First requested March 27; follow-up April 12. TCC SMEs participate in Budget Planning Tool workgroup.

7 Project Status – April 1 to 12, 2019
Overall Project Status Summary Category Status Comments Overall Y Program is on track, per timeline, scope and budget DG2 Training content development and UAT framework making good progress Security Mapping activities impacting UAT Schedule Monitoring scope and timing of Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Scope Requirements Traceability Matrix (RTM) needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Budget G Currently tracking under budget New Technology Plan approved as well as Stage Gate #3 for OFM/OCIO Technology Pool funding Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment continues due to the rework of key solutions. Each Deployment Group (DG) is now engaged in the project at some level. DG2 is in the Construct Phase and the ctcLink project team is performing DG2 System Integration Testing (SIT) and conversions. Conversations are underway to set go-live dates. DG3 is in the Structure Phase, focused on Business Process Fit/Gap sessions (BPFG) through May. DG4 is in the Initiation Phase, with most colleges nearing the halfway mark on deliverables. DG5 colleges have begun Initiation Phase and are learning the public status reporting process. DG5’s first report is included in this status update. DG6 will soon begin initiation phase and reporting process. The spring 2019 Project Managers Summit will be held at Wenatchee Valley College, with May 6-7 focused on overall Implementation Phase activities for all colleges and May 8 focused on the Initiation Phase for DG5 and DG6. Contract negotiations are underway for a new Continuing Education solution. The Online Admissions Application (OAA) work group is actively pursuing an OAA replacement. The Budget Planning Tool work group is reviewing and finalizing business and technical requirements. Overall Status Summary per Deployment Group DG# Status Comments DG2 Y Significant progress in the build of Training content and UAT Framework Security Mapping activities impacting UAT DG3 G College resources have been engaged in BPFG Workshops Conversion cycles have began DG4 DG5 DG 4 - College teams working on Initiation Phase activities DG 5 - Started tracking college Initiation and incorporated in status reports Christy Overall Timeline (All Deployments)

8 Budget Status – as of March 31, 2019

9 Deployment Group 2 Self-Reported Status – April 1 to 12, 2019
Clark College R Accomplished this period Continued to work on course catalog cleanup. Completed 7.5 hours of webex to review data validation materials for cycle 4. Prepared all materials for cycle 4 data validation. Financial Aid has planned out deadlines and system shut down for the Oct 28 Go Live. Planned for next period Continue to assign people and timelines to Change action work plan. Create an user group for current legacy users. Planned, but not completed *If status is yell or red, describe why. College is trending red due to discussion of date change for Go-Live. This has caused skepticism and uncertainty by SMEs and staff. UAT training plan also impacts college flexibility and schedule. Y SBCTC Agency Y Accomplished this period HR (non Payroll) business processes reviewed for change impacts 4/10 “Awareness” Overview for the agency conducted 4/3 Working with Bill Welch and Johnathan Rider on security mapping. The plan is to use elevated permissions for the first UAT Sprint. 4/11 Risk Management team formed completing initial meeting 4/1 Planned for next period Completion of Data Validation cycle #4 4/26 for HCM, 4/24 for FIN Follow-up ADKAR overview 4/22 Planned, but not completed n/a *If status is yellow or red, describe why. The Awareness overview has revealed a number of areas of opportunities to close gaps. Community Colleges of Spokane R Accomplished this period Chart of Accounts Redesign CCS Budget/Finance reviewing/validating mapping spreadsheets. 4/5 thru 4/19. In progress. FY Close – CCS continues to adjust journal entries. Uploaded schedule/Q&A/Check list to Box folder UAT’s for Student Billing, POI security issues, and SSN new query security tree. Planned for next period Security Role Redesign Security Issues *If status is yellow or red, describe why. Remediation Conditions involving Absence Management UAT and open items. FY16, 17 & 18 unable to close until cash reconciliation is completed. CoA Activities – reviewing local mapping files. Urgent Security Issues – sensitive financial and employee query data available across all FLCs. Security Role Redesign: waiting on documents to assist with role mapping, and cutover/implementation process. Concerns with newly communicated plan to test new security roles. Tacoma Community College G Accomplished this period Local SMEs attended ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in ctcLink Security redesign activities Participated Chart of Accounts meetings. Provided UAT testers to SBCTC. Attempted to reserve a dedicated ctcLink room for DG2 at Tacoma. Participated Cycle 1 Data validation meeting. Planned for next period Participate in Conversion Cycle Data Validation as needed Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Local SME participate in CE negotiations Local SME attend Chart of Accounts meetings

10 Deployment Group 3 Self-Reported Status – April 1 to 12, 2019
Cascadia College G Accomplished this period Attended all BPFG sessions to date Completed all but 2 BPFG homework assignments due this period Initiated CS and HCM data validation Planned for next period Continue data validation & OTM issue input for Cycle #1 Initiate DG3 Cycle #2 data error extract cleanup Continue BPFG attendance and homework completion Planned, but not completed Late completing 2 Finance BPFG homework assignments, Finance working with SBCTC CS Pillar PM to complete prior to 4/16/19 Lower Columbia College G Accomplished this period Work with Alignment Team to complete current BPFG sessions and homework Complete onboarding critical staff through PS fundamentals Work with staff to assemble training requirements and logistics for project team Onboarded LCC query developer team and started designing tracking mechanisms for query management Started work in Cycle 1 conversion validation work. Planned for next period Continue SME participation in all GDA and BPFG sessions as needed. This includes completion of CIA work as an outcome of BPFG. Continue on campus messaging and communication about ctcLink Continue to develop forecasting tools to track staff workload and project hours. Complete Cycle 1 conversation validation and start prep for Cycle 2. Peninsula College G Accomplished this period Continued to participate in BPFG sessions. Submitted BPFG homework assignments per BPFG session requirements. Organizing Data Validation efforts to meet April 24 deadline Planned for next period SMEs continue to participate in BPFG Sessions. Continue to coordinate and submit BPFG homework assignments Continue conversation regarding Go Live date. Complete Bio/Demo data validation for both CS and HCM. Pierce College District G Accomplished this period FIN & HCM SMEs participated in BPFG sessions. SMEs participated in Data Validation WebEx sessions. SMEs participated in CPW kick-off Completed all homework to date. Planned for next period SMEs complete data validation. SMEs attend/participate in BPFG sessions in person and via WebEx. SMEs complete homework assignments Planned, but not completed Complete additional Change Impact Analyses (CIAs). Review applicants for project positions. Onboarding of newly hired project employees. Review and update internal Training Plan with college Training Team. Olympic College G Accomplished this period Attended BPFGs Submitted BPFG Homework Continued Data Cleansing Started Data Validation Cycle Planned for next period Homework Data Cleansing Attend BPFGs Hire third Analyst Data Validation Planned, but not completed Additional CIA Workshops

11 Deployment Group 4 Dashboard Reports – April 1 to 12, 2019
DG4 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis College/District As of April 12, 2019 Centralia College 38% Edmonds Community College 60% Highline College 52% Seattle Colleges (3) 47% Wenatchee Valley College 45% DG4 Pre-Implementation and General Timeline G

12 Deployment Group 5 Dashboard Reports – April 1 to 12, 2019
DG5 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis College/District As of April 12, 2019 Bellevue College No Data Reported Bellingham Technical College 14% Big Bend Community College 11% Everett Community College 6% Grays Harbor College 19% Green River College Skagit Valley College 9% Whatcom Community College 17% DG5 Pre-Implementation and General Timeline G

13 PM summit Agenda Prep (Collaboration with College from each DG) Dates:
May 6 & 7 – All Colleges (Implementation Activities) May 8 - DG5 & DG6 (DG4 optional) focused on Getting Ready for Implementation (Initiation Activities) Location: Wenatchee Valley College

14 DEPLOYMENT GROUPS AND TIMELINE
Deployment Changes: Bellevue: DG4 to DG5 Columbia Basin: DG4 to DG6 Shoreline: DG5 to DG6 requested

15 INITIATION schedule highlights
This chart shows when each deployment group (DG) begins its first phase (initiation) and estimated Go-Live date. Dates subject to adjustment. Activity DG3 DG4 DG5 DG6 Begin Initiation Phase Work (Identify project manager, create project schedule, begin readiness efforts) Feb 2018 March 2018 July 2018 March 2019 Start Public Reporting (status reports, risks & issues) Dec 2018 Jan 2019 Nov 2019 Gate 1: Implementation Readiness July 2019 Oct 2019 July 2020 Implementation Phase Jan 2019 – Feb 2020 (Depends on DG2 Go-Live) Jan 2020 (Depends on DG3 Go-Live) Sept 2020 (Depends on DG4 Go-Live) Go-Live Feb 2020 Oct 2020 Feb 2021 Oct 2021 The time is now for all colleges to be engaged in ctcLink. Revised 2/20/2019

16 DEPLOYMENT GROUP ALIGNMENT
Background Shoreline Community College requests to move from Deployment Group 5 to Deployment Group 6. Discuss the impacts of adding a college to DG6 or leaving DG5 as is. Pros/Reasons for moving to DG6 Considerations Lack of readiness or participation in past and current PM/OCM activities Peer Review for DG5 colleges to enter implementation phase is only five months away Resource challenged with new interim PM Better for DG5 overall, because DG5 is the first deployment group with a technical college Risk to DG5 due to lack of readiness Reduces impact to DG6 At nine colleges, this makes DG6 the largest Resource strain on project staff for large DG6 Recommendations The ctcLink Project Management Office recommends granting Shoreline Community College’s request in order to minimize impact to both DG5 and DG6. To ensure college readiness, no further college movements are recommended within the deployment groups.

17 Online Admissions (OAA) Update
OAA Quick Wins (Current Improvements to Application in Production for FLC’s) Final Interviews with Colleges and Universities OAA Work Group feedback OAA Work Group Recommendation

18 Continuing Education Update
Negotiations Update Questions Global Approach for consistent student experience Pricing aligned based upon college size and enrollment Integration for ctcLink CampusCE baseline

19 Y ctcLink Quality Assurance Scorecard Overall Status
Moran Technology Consulting Report: March 2019 Overall Status Y ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018 STATUS PROJECT AREA DESCRIPTION / NOTES G SBCTC/Governance Governance framework continues to work as expected. Meetings are held according to schedule, with materials distributed beforehand, and decisions made at the appropriate level. Project Management Project Management Office (PMO) is fully staffed, working well together and continuing to address improvements in project management processes. Y Phase Scope QA concerned about implementation schedules for replacement solutions. Impacts to scope and schedule for DG2 and DG3 will be more defined once solutions are selected. Schedule Status DG2/DG3/DG4 schedules and resource constraints now directly impact all deployment groups. Schedule compression and key project resources are heavily allocated to tasks. Training The decisions and actions taken by PMO have enabled recovery of this key work stream. The external contractor supporting delivery of training materials has made good progress with the Finance and HCM pillars. PMO has decided to coincide just-in-time targeted training with UAT Sprints which achieves a number of positive benefits. Testing This work stream is yellow, but is now trending green due to changes made by the PMO. The PMO has added another PS experienced key resource for this work stream. DG2 Testing work stream relies heavily on availability and expertise of functional project staff. Configurations / Data Conversion Technical work for DG2 System Configurations and Data Conversion Cycle 4 is underway with good results reported. Organizational Change Management (OCM) PMO/OCM is actively engaged with all colleges now involved with their Deployment Groups. QA concerned that PMO focus remains on the DG2 schedule. Project Staffing Project staffing is adequate at this time and continues to make staffing adjustments as appropriate. QA and the PMO remain concerned that the overlap of DG2/DG3/DG4 may require additional project and contractor resources. Project leadership and staff morale is positive given schedule pressures. Technical Environment Future PS updates/bundles and 3rd party software installation and support work is being managed by the IT Division outside of the project responsibility. Overall planning of these changes needs to be tightly integrated with the ctcLink DG2/DG3/DG4 schedules. This becomes more challenging with the overlap in implementation schedules. LEGEND GREEN YELLOW RED Risk Description: Low risks may be encountered. NO immediate action needed Moderate risks may be encountered. Serious deficiency and action item recommended. High risks may be encountered. Needs to be escalated and can impact project effort or cost.

20 Other Discussion Items
-Executive Sponsor Engagement -cELC/President Engagement -SC Charter – Executive Sponsor Role Subgroup to review Steering Committee Charter Recommendations for addressing colleges in post- production that may no longer have an Executive Sponsor Executive Sponsor title is currently a requirement for nominee to serve on ctcLink Steering Committee

21 Questions?

22 Remediation Open – Finance
# Item # Description Status Planned Date Adjusted Date 1 19057 Ability for each organizational unit to develop and modify a budget at any level of the organizational structure and at any level of the program structure, throughout the budget development process. Open DG3 2/1/2020 Needs RFP 2 19297 Distribute and report labor costs based on user-defined criteria, with full integration and reconciliation of data between GL, Payroll, and Student. Closed 8/1/2018 Updated Training Content 3 19299 Provide a journal entry toolset, including but not limited to a standardize spreadsheet template, to facilitate streamlined journal entry and upload. 4 19304 Standardize sub-objects and mapping to a system-wide structure for each unique GL created at the college-level. 1/1/2018 7/1/2019 New COA Design 5 19323 Supports GL account verification across applications. 2/1/2018 TBD FY Deliverable 6 19342 Support vendor payment advance process based on user-defined criteria (e.g., each college is authorized to draw an advance against the State Treasurer, with the amount equal to 17% of preceding biennium's monthly allocation). 12/1/2017 SB Process Provided 7 19382 Integrate seamlessly with receivables processes to collect funds from vendors and recover overpayments.

23 Remediation Open – Finance, cont’d
# Item # Description Status Planned Date Adjusted Date 8 19454 Create and maintain as many payment forms and templates, including remittance detail, as required to meet institutional needs and local needs of individual colleges. Closed 8/1/2018 Updated Training Content 9 19633 Enable reconciliation process based on user-defined business rules (e.g., able to identify transaction source). Open 1/1/2018 TBD FY Deliverables 10 19747 Calculate and report indirect costs based on user-defined criteria. 2/1/2019 ERP Support 11 19968 Track grants separately from G/L Chart of Accounts and reconcile the two. 12 20212 Comparison of Actual to Budget (Revenues/Receipts and Expenditures) 12/29/2017 2/1/2020 Need RFP 13 N/A - 39 Must configure system to utilize correspondence to vendors for all PO’s. 1/1/2019 14 N/A - 41 College needs a budget development system that allows for adequate budget building process. DG3 15 19713 Dispose of financial and non-financial assets. DG2

24 Remediation Open – Human Resources
# Item # Description Status Plan Date Adjusted Date 1 20596 Faculty Workload to generate and modify documents and pay for adjunct faculty based on user-defined criteria (4 Phases to resolve / 2 Phases remaining) Closed 3/1/2018 Package /31/2018 Package 2 – 3/1/2019 2 29976 Develop and Re-run the ESD report 12/1/2017 TBD - TCC to Test 3 37532 Bio-Demo data values not aligned with CS and HCM 12/31/2018 4 20753 Establish contract pay based on user-defined criteria. Open 1/1/2019 TBD - Needs CPW 5 20573 Need ability to report on department budgets TBD Needs Budget Tool 6 N/A - 0 DRS Redistribution 4/30/2019 4/30/2019 – ERP SIT 7 N/A - 27 Step Movement / Needs CEMLI DG2 - 10/24/2019 In Development 8 N/A - 29 Spokane would like to participate in UAT process for upcoming DGs implementing the Recruitment module. DG2 4/29/2019 9 N/A - 31 Migrate ctcLink framework to Wave 1 framework (related to Absence Management) 10 N/A - 32 Create “day” definition / Absence Management and Time & Labor issue 11 N/A - 34 Provide list of employees missing area codes / Legacy Data Issue 9/14/2018

25 Remediation Open – Campus Solutions
# Item # Description Status Planned Date Adjusted Date 1 20797 Support continuing education registration process where student can browse courses without logging on Open DG3 2/1/2020 In Negotiations 2 20901 Provide the ability for continuing education students to enroll directly in classes (i.e., application is not required). 3 21359 Allow payment online for continuing education based on user name and password. 4 21505 Perform third-party billing based on user-defined criteria (e.g., by student, consolidated) . Closed 5/1/2018 10/24/2019 GDR Approved 5 20814 6 21293 Support streamlined admissions processing and user interface. (Online Admissions Application) Evaluation 7 N/A - 13 Effective Dating: FA Term, FA Budget and other areas have defective Effective Dating 12/1/2017 TBD 8 N/A - 15 Reconciliation queries haven’t worked correctly or accurately since Go Live. 3/1/2018 5/30/2019 FY Deliverable 9 N/A - 22 Error/exception report identifying discrepancies between financial aid system and the general ledger (2nd Journal Set)

26 Remediation Open – Campus Solutions, cont’d
# Item # Description Status Planned Date Adjusted Date 10 N/A – 12 SAP Setup Effective Dating doesn’t work (Oracle Bug ID ) Open 6/1/2018 TBD Waiting on fix from Oracle Workaround in place 11 N/A – 17 Converted student account balances must be completely audited / corrected to reflect the ending balances from Legacy. 5/30/2019 FY Deliverable 12 N/A – 18 Reports to reconcile student financial transactions for a given day to the general ledger by item type, chartstring and fund. 5/1/2018 13 N/A – 19 Need accurate reports in the CS pillar for Student Financials to summarize data such as insurance, fees, waivers, etc. 9/30/2018 14 21451 Maintain academic standing for financial aid eligibility, based on multiple, user-defined criteria Closed N/A 15 21338 Track satisfactory academic progress (SAP).