The Anschutz Health Sciences Building Construction Update 8 April 2019
2
Agenda Current and Upcoming Activities
R2 Impacts and Mitigation Efforts Agenda
3
Current and Upcoming Activities
4
Lagging and Excavation, including S Tunnel: Complete by April 17
North Tunnel: Excavation, East 3rd week of June, West 2nd week of October Drilled Cassion’s: Complete By May 24 Concrete foundations, Walls, etc.: Start April 26th Tower Crane Install: End of April
5
R2 Impacts and Mitigation Efforts
6
Research 2 Impacts Air Intake Mitigation Efforts Equipment Requirements: Tier 4 Intake Filters: Completed on March 12 Air Diffuser Filters: Installed at areas of concentrated concern R1 and R2 Intake Monitoring: Reports available starting on March 13. AHSB Project has purchase forty (40) Charcoal filter air cleaners, which will be installed throughout R2. Review of alternate entry points, i.e. R2 loading dock Information can be found on the Facilities Active Projects website Contact Information Doug Wilson,
7
Air Flow Diagram