1 Software Effort Estimation

2 Presentation Summary Introduction Estimation Techniques
Why do we Estimate? When do we Estimate? What do we Estimate? Guidelines for Estimation Estimation Techniques LOC COCOMO-I and II Function Points

3 SENG 621 - Software Size Estimation
Introduction – Why? Industry has a reputation for software being over budget, late in delivery and low quality. Unreasonable time and budget Client satisfaction cannot be achieved with poor quality software even if it is on time and on budget. SENG Software Size Estimation

4 SENG 621 - Software Size Estimation
…Introduction – Why? To avoid this, means must be developed to accurately predict: The resources needed to generate the deliverables Accurately predicting the size of a project results in better project planning. SENG Software Size Estimation

5 SENG 621 - Software Size Estimation
…Introduction – Why? To analyze past projects and apply lessons learned from bad estimates. SENG Software Size Estimation

6 SENG 621 - Software Size Estimation
…Introduction – When? As early as possible in the project. “At no other time are the estimates so important than at the beginning of a project” Estimation is an iterative process, occurring many times though out development. After requirements, analysis, design, coding, testing, etc… SENG Software Size Estimation

7 SENG 621 - Software Size Estimation
…Introduction – When? Whenever new information that affects the project becomes available. “Predicting the size of a software system becomes progressively easier as the project advances” SENG Software Size Estimation

8 SENG 621 - Software Size Estimation
…Introduction – What? Different phases in development can be estimated: Requirements Documents Design Documents Code Test Cases Generally what is needed is an idea of the scope of the project. Getting a feel for the size of project can indicate how much of everything else is needed. SENG Software Size Estimation

9

10

11

12 Example

13

14

15

16 Function Points ( FP ) The approach is to identify and count a number of unique function types: external inputs (e.g. file names) external outputs (e.g. reports, messages) queries (interactive inputs needing a response) external files or interfaces (files shared with other software systems) internal files (invisible outside the system)

17 Unadjusted function points
Unadjusted function points ( UFP ) is calculated as follows : The sum of all the occurrences is computed by multiplying each function count with a weighting and then adding up all the values.

18 Albrecht’s original method classified the weightings as:
Function Type Low Average High External Input x3 x4 x6 x5 x7 Logical Internal File x10 x15 External Interface File External Inquiry

19

20

21

22

23 Calculate FP

24 Table given

25 Ex:The ATTEND MASTER - Data Flow Diagram

26 Calculation of CFP Crude Function Points
Analysis of the software system as presented in the DFD summarizes the number of the various components: ■ Number of user inputs – 2 ■ Number of user outputs – 2 ■ Number of user online queries – 3 ■ Number of logical files – 2 ■ Number of external interfaces – 2. The degree of complexity (simple, average or complex) was evaluated for each component.

27 Calculate FP

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44


Download ppt "Software Effort Estimation"