29th & Choctaw Rd Project Projected time line.

Similar presentations


Presentation on theme: "29th & Choctaw Rd Project Projected time line."— Presentation transcript:

1 29th & Choctaw Rd Project Projected time line

2 Currently: South side, north & southbound lanes closed

3 August 18th The whole intersection will be closed down for traffic in all directions. Anticipated opening back up on August 28th for north and south bound traffic.

4 August 28th, open up to north south traffic, close down west side of intersection for all east west traffic. Anticipated opening September 5th.

5 September 5th, close east side of intersection for all east west traffic. Anticipated opening on September 18th

6 September 18th, close down north side of intersection to north and southbound traffic. Anticipated opening September 26th.

7 We ask our citizens to be patience with us as we work to make these permanent repairs to this intersection. With favorable weather we should make this timeline. If we experience rain this may cause the timeline to extend, as we will be unable to do base work or concrete pours in this.