QUADCOPTER PRODUCTION PLAN
2
OUTILLAGE Hex wrench 2.5 mm Open-end spanner 5.5 mm Hex wrench 2 mm
3
-Set the arm supports without screwing it on the x500mm Big Arm
4
-Set x500mm Big Arm and his Arm supports on the Uper shell
Upper Shell (10) 205 mm 205 mm 80 mm
5
-Set the arm supports on the upper shell without screwing them.
-The screws not screwed will be used to fix the attachment pillar. Arm Support (8)
6
M3 Nut (1) -Block the 245 little arm in the arm support that have the same centering as the x500mm Big Arm. M3x25 Screw (3)
7
-Set the attachment pillar on the arm supports.
M3 attachment pillar (7) M3 attachment pillar (7)
8
-Screw the lower shell on the M3 attachment pillar with the M3 screws.
M3 Nut (1)
9
Assembling of the landing gear:
Set the 2 landing gears against the M3 Spacer landing gear then fix it with the 2 M3x5 Screw. At the same time place the large partie of each landing gear on the arm support and screw it with the 2 M3x25 screw and the M3 Nut. Landing gear M3 Nut (1) M3x25 Screw (3) Arm Support (8) M3x5 Screw (5) M3 Spacer Landing gear (6) Assembling landing gear
10
-Fix the 4 landing gears on the 4 arms.
They need to be fixed at the extremity of the arms. Arm Landing gear
11
Frame of the drone assembled: