PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL.

Similar presentations


Presentation on theme: "PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL."— Presentation transcript:

1 PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL

2 PRESENTATION OUTLINE Background RHIP Overview RHIP Objectives
Roles and Responsibilities Progress per Province – 2010/11 Challenges – 2010/11 Progress per Province – 2011/12 Financial Performance – 2011/12 Job Creation – 2011/12 Challenges – 2011/12 Way Forward – 2012/13 & 2013/14

3 Draft and Confidential
Background In May 2009 State President announced transfer of sanitation function from DWA to NDHS There were other departments that were also affected by re-organisation of State e.g. Education and Minerals and Energy The legalisation of the movement was not done and we focused on staff transfer Staff transferred were component dealing with basic sanitation, high level of sanitation still at DWA Draft and Confidential

4 RHIP OVERVIEW The Rural Household Infrastructure Programme is a special four year programme to provide basic sanitation (and water) to rural communities. It has been allocated a total budget of R1.2 billion. The budget is allocated to the NDHS as a Schedule 7 Grant - NDHS appoints IAs & enters SLAs with WSAs. The budget split over the MTEF is: 2010/11: R100 million; 2011/12: R231,5 million; 2012/13: R479,5 million and 2013/14: R389 million.

5 RHIP OBJECTIVES To support municipalities to address rural basic sanitation (and water supply) backlogs. To improve the quality of life in rural communities. To contribute to the rural development priority of government. To contribute to job creation and Local Economic Development. To contribute towards meeting the sanitation (and water supply) MDG targets of South Africa. To accelerate delivery of sanitation (and water supply) to meet the 2014 target.

6 Roles and Responsibilities of Implementing RHIP-
By nature of the grant being gazetted as Schedule 7, it means, even though it is gazetted against municipalities, it is not transferred to municipalities; it is managed by the National Department. National Department is responsible for the identifying mechanisms of implementation being usage of Implementing Agents which could be NGOs, CBOs, Public Entities or Managing Contractors. National Department needs to agree with municipalities on the scope of the work to be done. This is for the purpose of aligning the RHIP projects municipal IDPs. This necessitates identification of specific areas of operation up to ward level. National Department needs to agree with municipalities on issues of operation and maintenance of the infrastructure

7 Roles and Responsibilities of Implementing RHIP (cont…) National Department and Municipalities
An agreement between the National Department and the municipalities regarding the scope of work needs to be reached; that is, identification of specific areas of operation up to ward level. Municipalities will ensure RHIP projects appear in their IDPs. All parties will be expected/ required to attend site meetings to monitor progress, and identify means of interventions should there be problems during the implementation.

8 PROGRESS PER PROVINCE - 2010/11
Allocation: 2010/2011 (R’000) Number of Benefiting Municipalities Target Number of VIP Toilets VIP Toilets completed at 31 March 2012 % Completion Eastern Cape R18,000 5 2,559 100% Free State R3,000 1 300 Limpopo R27,000 9 3,600 3,376 94% KwaZulu-Natal 7 3,674 Mpumalanga R4,000 515 Northern Cape 400 North West R6,000 2 828 National Prog. Management R12,000 Grand Total R100,000 26 11,876 11,652 98%

9 CHALLENGES /11 Programme started in Oct 2010 (procurement delays). Some WSAs did not fully grasp the nature of Schedule 7 Grant and delayed signing SLAs with NDHS as they wanted to implement the programme themselves. Excessive rainfall was experienced during December 2010 and January 2011 which caused delays. Implementing Agents struggled to source building material and have it delivered on site on time. Some contractors struggled with difficult ground conditions i.e. hard rock and high water table.

10 PROGRESS PER PROVINCE - 2011/12
Allocation: 2011/2012 (R’000) Number of Benefiting Municipalities Number of VIP Toilets targeted VIP Toilets completed as at 31 May 2012 % Completion Eastern Cape R65,000 13 7,462 7,185 96% Free State R10,000 3 1,297 1,198 92% Limpopo R48,000 12 5,864 4,081 70% KwaZulu-Natal R68,000 15 7,967 7,137 90% Mpumalanga R8,000 2 1,038 1,023 99% Northern Cape 1 507 486 North West R28,000 7 3,551 2,979 84% Grand Total R231,500 53 27,686 24,089 87%

11 FINANCIAL PERFORMANCE - 2011/12
Province 2011/12 Allocation & 2010/11 Rollover Provisional Expenditure at 31 March 2012 Work in Progress KwaZulu-Natal R80,487,091 R63,207,997 R17, 279,094 Eastern Cape R65,000,000 R55,868,072 R9,131,928 Limpopo R54,552,091 R26,688,032 R27,864,059 North West R30,063,533 R22,711,497 R7,352,036 Free State R12,924,676 R8,548,344 R4,376,332 Mpumalanga R10,086,447 R7,943,553 R2,142,894 Northern Cape R4,394,162 R2,298,425 R2,095,737 Grand Total R257,508,000 R187,265,920 R70,242,080

12 JOB CREATION - 2011/12 Province No of Benefiting Municipalities
Estimated Target No. of VIP Toilets Temporary Jobs Created as at 31 May 2012 Eastern Cape 13 7,462 1,372 Free State 3 1,297 181 KwaZulu-Natal 15 7,967 1,254 Limpopo 12 5,864 867 Mpumalanga 2 1,038 324 Northern Cape 1 507 70 North West 7 3,551 658 Grand Total 53 27,686 4,726

13 CHALLENGES /12 The 2 appointed Implementing Agents (Mvula Trust and IDT) were not sufficient to implement such a programme at scale and achieve the outcomes set. The existing SLAs between the NDHS and the Programme Management Support PSP (Maxima Global/TranSpace) on one hand and Mvula Trust and IDT on the other were not consistent with each other. The process of handling claims of the Implementing Agents needed to be restructured to assist them with improved cash-flow management.

14 CHALLENGES /12 cont… The recovery plans submitted in Sept 2011 by the 2 Implementing Agents were too optimistic. The IAs ability to procure building materials from suppliers in large quantities posed a serious challenge to the outcomes of the programme. The scope of work approved for the IDT was at high risk of not being completed by end of the 2011/12 financial year. In December 2011 NDHS re-allocated 7,098 units from IDT and negotiated with Mvula Trust to complete these units by the end of the 2011/12 financial year.

15 MIG National Allocations
Province 2012/13 (‘000) 2013/14 (‘000) 2014/15 (‘000) EC FS GP KZN LP MP NC NW WC Total Draft and Confidential

16 Operation and Maintenance
In terms of the 2012 Division of Revenue Act, within the Basic Service component of the Equitable Share, there is a breakdown of the allocation between water, sanitation and refuse removal. These funds are for operation and maintenance which include emptying of full pits and septic tanks. Draft and Confidential

17 WAY FORWARD /13 & 2013/14 NDHS has reduced the previously budgeted allocations of IDT and Mvula Trust to a total of +/-60% of the 2012/13 budget (in line with NDHS Portfolio Committee recommendations). NDHS is currently in process of putting the +/- 40% balance of the 2012/13 budget to tender for additional Implementing Agents to be added to the programme. The SLA of the Programme Management Support PSP is to be aligned to the performance of the IAs. In 2012/13 both machinery & manual labour will be used in difficult ground conditions where needed.

18 Draft and Confidential
WAYFORWARD Cont. Process of drafting proclamation for sanitation transfer has started We are also negotiating with DWA in lieu of Water Services Act amendment Seeking legal advise on implementing an Act that is managed by another Department We need to discuss with CoGTA to synchronise planning and management of sanitation We need to talk to National Treasury to strengthen sanitation reporting by WSAs Draft and Confidential


Download ppt "PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 17 AUGUST 2012 By MR T ZULU DIRECTOR GENERAL."