1
PSO Reliability/System Engineering
CVR and BEYOND PSO Reliability/System Engineering
2
CVR – The Basics
3
CVR Year One 4 Substations 9 Transformers 24 Circuits
119 Capacitor Banks 6 Three Phase Voltage Regulators 95 End of Line (Voltage) Monitors
4
Challenges: CVR Year One New control system. New capacitor controls.
New RTUs. New EOL devices. New team.
5
CVR Year One
6
CVR Year One
7
CVR Year One
8
CVR Year One
9
CVR Year One
10
CVR Year One
11
CVR Year One
12
CVR Year One
13
CVR Year One
14
CVR Year One
15
CVR Year One
16
CVR Year One Lessons Learned
Communicate clearly with Procurement groups. Communicate clearly with Substation groups. Communicate clearly with Telecom groups. Communicate clearly with Construction groups. Communicate clearly with Dispatch groups. Communicate clearly with DMS groups.
17
CVR Year One Afterthoughts: Be flexible (relatively)
Be prepared to explain yourself Be prepared to receive criticism (constructive and otherwise) Be prepared to learn.
18
Feeder 31 – Voltage Investigation
19
Feeder 31 Overview
20
Feeder 31 Overview
21
Feeder 31 Overview
22
Feeder 31 Voltage Profile