Presentation is loading. Please wait.

Presentation is loading. Please wait.

EASTERN CAPE HOUSING DELIVERY

Similar presentations


Presentation on theme: "EASTERN CAPE HOUSING DELIVERY"— Presentation transcript:

1 EASTERN CAPE HOUSING DELIVERY
REVIEW FOR THE FIRST 9 MONTHS OF THE 2006/07 FINANCIAL YEAR

2 PRESENTATION OVERVIEW
FINANCIAL & NON-FINANCIAL DELIVERY OUTPUTS IDENTIFIED PERFORMANCE CONSTRANTS Strategic, with the related Operational impacts REMEDIAL INTERVENTIONS: THE PARADIGM SHIFT … UPDATE ON INTERVENTIONS UNDERTAKEN CONCLUSION

3

4 EXPENDITURE vs CASH FLOW FORECAST IN DISTRICT ORDER

5 NON-FINANCIALS…

6 OUTPUTS FOR THE 1ST 9 MONTHS
Number of emergent contr Jobs created Houses completed Subsidies approved Title Deeds transferred Municipalities accredited (in process) 2 Disaster housing assistance 100

7 NEGATIVE FACTORS INFLUENCING HOUSING DELIVERY.
STRATEGIC CONSIDERATIONS… The challenges facing E/Cape housing delivery must be seen against the following strategic approaches, initially undertaken for developmental reasons: Use of PHP delivery vehicle – (60% of E.C. projects are PHP) (slow delivery due to layered coordination & communication processes) Majority of Developers are Municipalities Use of Emerging Contractors 40 sq.m. size unit on 30sq.m National Norm Allocation – (Unfunded extra 10m²) The negative impact of these factors has been building up over the years to what is now possibly the highest point

8 HOUSING RECOVERY INTERVENTIONS
Departmental take-over of some of the unblocked projects which are slow-moving through engagement of Established Contractors inclusive of Thubelisha Addresses twin-problem of Municipal and Emerging Contractor capacity shortfalls The involvement Established Contractors allows for a number of advantages: Speedier Procurement Processes Bulk material purchases Sourcing of additional resources to reinforce existing construction teams

9 HOUSING RECOVERY INTERVENTIONS (ROLE OF ESTABLISHED CONTRACTORS)
The Established Contractors are performing the normal contractor role, inclusive of: Execution of Construction Works to Scope, Budget, Spec, Schedule (Penalty clauses to be enforced) Materials and labour procurement Site Management ; Handover of Works Key Ingredient Embracing emerging contractors in order to mentor them to graduate to higher skills & expertise levels within requirements of allocating projects to them in accordance with requisite capacity

10 PROGRESS TODATE A fast-tracked procurement process affecting a total of 18 projects ( combined value R433m) will ensure on-site activity early in March Projects in new financial year are being packaged for execution through Established Contractors. A quantum leap in provincial delivery is envisaged

11 CONCLUSION 1. The Department is confident that the dominant elements of the delivery under-performance problem have now been exposed, and are being dealt with in a meaningful way. 2. Even though the paradigm shift and strategic intervention currently embarked on will only begin to take effect at the tail-end of current financial year, a solid basis has been laid for higher-level delivery performance in the remainder of the MTEF cycle

12 Thank You Comments & Questions


Download ppt "EASTERN CAPE HOUSING DELIVERY"

Similar presentations


Ads by Google