1 MVB-II Assembly Instructions
©  All Rights Reserved to Mifram Ltd. 2018

2

3 About the MVB-II The MVB 2 is an advanced and improved version of the original Mifram MVB The overall principle remains the same When assembled units vertical element is impacted diverting the horizontal momentum into the ground The placement of the MVB is crucial. The Pictures demonstrate the correct orientation of the units The open side of the L shaped unit is the side to face the threat and receive the impact Tested & Approved:

4 Deployment Recommendations
If Possible, deploy the MVB-II where the ramming car will be situated in the lower speed by using natural obstacles like curves etc. Block road sides and side walks. Use warning lights and signs.

5 Orientation of Elements in direction of potential threat
(Open L shape) in direction of potential threat Direction of Potential Threat MVB – II Deployment

6 Safety Warning Be aware that several parts are heavy (26 kg) and sharp, pay attention during unloading, assembling and packing Elements Placed upright prior to being joined can fall on their side and create a hazard

7 The complete MVB-II

8 MVB-II Parts

9 R Pin

10 Handle

11 Rod & End Unit

12 Pull out the safety R pin

13 Pull out the safety R pin

14 Pull out the locking yellow pin

15 Pull out the locking yellow pin

16 Lift the upper part

17 Lift the upper part and Insert the locking yellow pin

18 Insert the locking yellow pin into the right hole
The wrong hole The right hole

19 Insert the locking yellow pin into the right hole
The wrong hole

20 Insert the safety R pin

21 Insert the safety R pin

22 Safety pin placed in the locking pin

23 Assembling of the units one after the other
Repeat the above steps as needed in order to get required barrier width

24 Start on left side, insert rod

25 Insert the Rod B’H

26 Insert the Rod to the next unit

27 Add the second rod

28 Commence second section Insert second wheel section

29 Insert large safety pin

30 Insert large safety pin and lock it with the spring

31 Assembled and secured rods

32 Assembled 2 units with rods
Repeat the above steps as needed in order to get required barrier width

33 MVB-II Assembling First Meter
Exercise Care Units when opened and in standing position can tip and fall sideways. In order to prevent this, keep all units laying on their side on the ground surface until you are ready to join them.

34 Repeat the above steps

35 Assembling of the last right side unit

36 Assembling of the last right side unit

37 The End Unit

38 Insert the End Unit

39 Insert large safety pin and lock it with the spring

40 Assembled units without handle
Place of handle

41 Attach the handle

42 Secure the handle with safety pin and lock it

43 MVB-II with rods & handle

44 Next step Assembling of the upper and lower cross section bars

45 Pull out the safety R pin from the upper cross section bar

46 Pull out the yellow pin and lift the upper cross section bar

47 Insert the yellow pin, Always from the front side

48 Secure with the R pin from the back side

49 Pull out the safety pins from the lower cross section bar

50 Move it to the right position

51 Secure the lower cross section bar with the safety and the R pin

52 Insert the R pin

53 MVB-II is ready for operation

54 Please contact us Thank you for purchasing Mifram MVB-II.
with any question or information you may have. Our customer support will be happy to help you. ©  All Rights Reserved to Mifram Ltd. 2018


Download ppt "MVB-II Assembly Instructions"

Similar presentations


Ads by Google