LCLS-II Cryoplant Controls Workshop.

Similar presentations


Presentation on theme: "LCLS-II Cryoplant Controls Workshop."— Presentation transcript:

1 LCLS-II Cryoplant Controls Workshop.
Installation Schedule / Milestones toward Pre-com Vincent HELOIN, SLAC Cryogenic Group December 5th, 2018

2 3.CP : Cryoplant Installation Plan

3 3. Contract Performance Periods
Based on GFP Equipment List Rev A dated February 16th (IFC)

4 CP. GC Contract Performance Periods
Perf A – Jan ‘19 Perf B – May ‘19 Perf C – Aug ‘19 Perf D – Jan ‘20

5 CP. GC Contract Performance Periods
Priority of installation provided through the :”installation Guidance” established in September 2019 through annoted PID PID is a key tool to : Setting installation priority and communicate. Ensuring a safe installation acceptance (Pressure test network) Ensuring a safe anticipated commissioning of subsystem by ensuring proper isolation are in place and that sensors are well positioned…

6 GFP List Update A revised GFP list was provided on August 17th (PCO 004.1) KSI issued a new schedule showing the impact on completion of each performance period. This scheduled has been incorporated in BCR CS-113 and baseline P6 Further Delays tracking SLAC provides update to the GC weekly, at the OAC meeting. The GC integrates the deliveries status and distribute it part of the OAC minutes of meeting LCLS-II Collab. Meeting, May 25th,2018

7 CP. GC – Activities Scheduling
The GC has developed a full detailed P6 schedule >1000 activities Occupancy A March 29th Completion A May 20th SLAC P6 contains the 66 lines that composed the Schedule of Values

8 CP. GC – Activities Scheduling
Each performance period is decomposed similarly

9 CP. GC – Activities Scheduling
The GC has developed and maintained a detailed P6 schedules shared with SLAC and JLAB. Different views are provided : High Level Milestone Forecast Full Schedule Forecast 8Weeks look ahead (updated weekly) Owner Critical Path A Owner Critical Path B Owner Critical Path C Owner Critical Path C1 Owner Critical Path C2 Owner Critical Path D Owner Critical Path Project High Level milestone (dated from Nov 9th)

10 CP. GC – Main Milestones Each performance period A / B / C and D are not well indicated into P6. It would be easier to simply add a clear milestone for each performance Period that would allow a simple link with Jlab commissioning activities  to be done Certificate of occupancy (acc to GFP as per Nov 9th) Performance A March : Start Purification Owner Critical Path B July 17th : Start 4K Owner Critical Path C Nov 7th : Start 2K Owner Critical Path D Dec 4th : C1 & C2 Completed (start C2) Certificate of occupancy is not the completion milestone ! Recent delays (Purifier, LN2 Tank, LCB, Analyzers, Gauge Panel, vaporizers) and ongoing resolution (tubing not part of the work planned) are not yet captured. COMPLETION PHASE A MOST LIKELY TO BE JUNE 2018

11 6. LOOK-AHEAD: Overall Schedule – June 2018
FY2018 FY2019 FY2020 C1 LCB C2 UCB Sep ‘18 Apr. 2019 DELIVERIES... June 2018 Feb. 2020 Installation Feb. 2019 Feb. 2020 Jul. 2020 Commissioning CP1 CP2 TTO Mar. 2020 LINAC COLD TTO Transfer To Operation: After 2K.CB tests or after LINAC Cool-Down, tbd.

12 6. LOOK-AHEAD: Overall Schedule – Nov 2018
FY2018 FY2019 FY2020 C1 LCB C2 UCB Sep ‘18 C1 LCB Jan ‘19 June. 2019 DELIVERIES... June 2018 Feb. 2020 Installation May. 2020 April. 2019 Jul. 2020 Commissioning CP1 CP2 TTO Mar. 2020 LINAC COLD TTO Transfer To Operation: After 2K.CB tests or after LINAC Cool-Down, tbd. Commissioinng :40days for the 4K and 40 days for the 2K