Download presentation
Presentation is loading. Please wait.
1
Operations Research Lecture 8
2
Operations Research CPM / PERT
3
OR PROCESS OBSERVATION PROBLEM DEFINITION MODEL CONSTRUCTION SOLUTION
H N I Q U S MODEL CONSTRUCTION SOLUTION IMPLEMENTATION
4
… OVERHAUL Plant, Equipment, Vehicle CONSTRUCTION
Flats, Houses, Offices CIVIL ENGINEERING Bridges, Roadways TOWN PLANNING Control of design procedures …
5
MARKETING Product launching SHIP BUILDING Designing and Production DESIGNING Car, Machine Tools OFFICE PROCEDURE CONSULTANCY, etc.
6
Critical Path Method (CPM)
Networks Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) Network Flow
7
Example:A project has the following relationships among the activities
Example:A project has the following relationships among the activities. Construct the network. A is the first operation. B and C can be performed parallel and are immediate successors to A. D,E and F follow B. G follows E. H follows D, but it cannot start till E is complete. I and J succeed G. F and J precede K. H and I precede L. M succeeds L and K. The last operation N succeeds M and C.
8
7 H 5 4 F E D L 8 I J 2 1 A 3 B 6 G 9 K 10 M 11 N C
9
A is the first operation.
The last operation N succeeds M and C. A is the first operation. 7 H 5 4 F E D L 8 I J 2 1 A 3 B 6 G 9 K 10 M 11 N C B and C can be performed parallel and are immediate successors to A. H follows D, but it cannot start till E is complete. D,E and F follow B. G follows E I and J succeed G. F and J precede K. H and I precede L M succeeds L and K.
10
TIMES (ACTIVITY) EARLIEST START TIME
Earliest possible time at which an activity can start and is given by the earliest time of the Tail Event. 1 2 7
11
TIMES (ACTIVITY) EARLIEST FINISH TIME
Earliest possible time at which an activity can finish and is given by adding the duration time to the earliest start time. 1 2 7
12
TIMES (ACTIVITY) LATEST FINISH TIME
Latest Event Time of the Head Event. 1 2 7
13
TIMES (ACTIVITY) LATEST START TIME
Latest possible time by which an activity start and is given by subtracting the duration time from the Latest Finish Time. 1 2 7
14
Example 2 5 6 8 1 2 3 4 4 3 7 4 6 8 5 9 6
15
Cont ! 5 2 3 4 7 8 6 E=11 E=1 E=8 E=6 E=0 2 6 8 1 L=12 L=10 4 3 E=15
9 6 L=6 L=21 L=15 E=15 L=0 L=10 L=15
16
E=11 E=1 E=8 E=6 E=0 2 5 6 8 1 2 3 4 L=12 L=10 4 3 7 E=15 E=21 4 6 8 5 9 6 L=6 L=21 L=15 E=15 L=0 L=10 L=15
17
E=11 E=1 E=8 E=6 E=0 2 5 6 8 1 2 3 4 L=12 L=10 4 3 7 E=15 E=21 4 6 8 5 9 6 L=6 L=21 L=15 E=15 L=0 L=10 L=15
18
FLOATS INDEPENDENT FLOAT
Time by which an activity can expand without affecting other (PREV or SUBSEQ) I = jE - iL - D If Negative, take I = 0
19
Cont ! FREE FLOAT Time by which an activity can expand without affecting subsequent activity. F = jE - iE - D
20
Cont ! TOTAL FLOAT Time by which an activity can expand without affecting the overall duration of the project. T = jL - iE – D
21
Operations Research Lecture 8
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.