Download presentation
Presentation is loading. Please wait.
1
LINK BOARD PROJECT UPGRADE
Pigi Paolucci and Napoli group
2
Outline LB CAD project LVDS suppressor studies LV regulator studies
Open questions To be done Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
3
LV Regulator LHC4913 Pigi Paolucci
Link Board Upgrade Meeting - Dec 2010
4
LB project schema Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
5
Test schema LHC4913 Pigi Paolucci
Link Board Upgrade Meeting - Dec 2010
6
Temperature Tests Vin = 5V Vout = 3.3V Iout = 1.4A (Load=2.3W//2200uF); Ta = 27°C; Td = 91°C 1 volt 1 msec Vin Vout 2 msec Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
7
Rumping up and down Vin Vout Vin Vout Pigi Paolucci
Link Board Upgrade Meeting - Dec 2010
8
Temperature Tests Vin=5V; Vout=3.3V Iout=2.6A (Load=1.2W//2200uF); Ta=27°C; Td=135°C 1 volt 1 msec Vin Vout Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
9
Rumping up and down Vin Vout Vin Vout Pigi Paolucci
Link Board Upgrade Meeting - Dec 2010
10
Different Loads Vin=5V; Vout=3.3V Iout1=1.4A (Load=2.3W//2200uF) Iout2=2.6A (Load=1.2W//2200uF) Vin Vout Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
11
How does react to input spikes
Vin=5V; Vout=3.3V Iout1=1.4A (Load=2.3W//2200uF) Spike=5V / Vin=10V Spike su Vout > 10mV Vin Vout Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
12
Heat Dissipation Tmax (junction) = 125°C; Rcase (junction) = 2°C/W (datasheet) Working case Vin = 5V; Vout = 3.3V; Iout = 1.5A Power to dissipate = (5V - 3.3V) * 1.5A = 2.55W; Tamb=25°C Rtot = DT/W = (125°C – 25°C)/2.55W = 39°C/W Rheatsink = Rtot-Rjc = 37°C/W Worst case Vin=6V; Vout=3V; Iout=3A Power to dissipate= (6V – 3V) * 3A = 9W; Tamb = 40°C Rtot = DT/W = (100°C - 40°C)/9W = 6.6°C/W Rheatsink = Rtot-Rjc = 4.6°C/W Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
13
Max temperature behaviour
Test Conditions Vin=6V; Vout=3.3V; Iout=2.6A; Tamb=25°C Temperature on the case: 155°C -:- 135°C Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
14
Regulator Infrared scan
Standard condition Worst case – before shutdown Worst case – after shutdown Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
15
Costs needed spare PCB + mount + test components cost Total Crates 12
€100,0 €1.400,0 ControlBoard 24 4 €430,0 €362,0 €792,0 €22.176,0 Link Board Master 48 5 €200,0 €450,0 €650,0 €34.450,0 Link Board Slave 96 10 €400,0 €600,0 €63.600,0 BackPlane €337,0 €395,0 €732,0 €10.248,0 Frontplane €99,0 €75,0 €174,0 €4.872,0 Mod APA450 €146,0 €385,0 €531,0 €14.868,0 Mech. €37,5 €30,0 €67,5 €1.890,0 € ,0 Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
16
Time schedule Installation and commissioning in the 2013 2011 2012 J F
LB prototype LB test CB prototype CB test Lbox production Test 904 Installation and commissioning in the 2013 Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
17
Manpower and tasks Napoli is interested in the design of the “up-to-date” system P. Paolucci, S. Buontempo, N. Cavallo (sabbatical year in the 2011) Electronic Service: 6-7 months in the 2010 and 2011 Napoli is now (2010) designing the “up-to-date” LB system including: LVDS suppressor, LV regulators. First design almost ready (80%). Cost estimation ready LNF is looking at the test and commissioning of the system L.Benussi, L.Passamonti (Tech.), D.Pierluigi (Tech.) and Electronic Service: 3-4 months in 2011 Warsaw is in charge for the test, commissioning and installation of the system Warsaw is the only group having the full expertise of the link board hardware and firmware system The participation of new groups at the LB project has been strongly recommended by the CMS management Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
18
Manpower needed ? Prototypes test at CERN: 1 tech + 1 phys for 3 months (2011) + Warsaw Test at CERN (blg 904): 1 tech + 1 phys for 6 months (2012) + Warsaw Installation: 2 tech + 1 phys for 6 months (2013) + Warsaw Commissioning: 1 phys for 3-4 months (2013) + Warsaw Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
19
To be done Document about the project, schedule, manpower and responsibilities: Napoli, LNF and Warsaw ?: Napoli and LNF: production Warsaw, Napoli and LNF: prototype test at 904 Warsaw, LNF and Napoli: Production test and commissioning New design: regulators + heat sink + what else ? LV board: new firmware + what else ? What about the spares ? Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
20
Conclusion Preliminary conclusions of the Electronic Service in Napoli: The present project is very good, complex and sophisticated; congratulation to our Warsaw/Finland colleagues Two “rad-hard” LV regulators per boards (LB/CB) are suggested – heat dissipation to be studied very carefully Not clear if we really need a set of LVDS protections Spartan III configuration could be double checked New LB boxes and boards can be produced in Italy but only Warsaw experts can test and commissioning the full system – Napoli and LNF will be part of the business but not the main actors INFN will discuss and decide about the project in Jan 2011 Pigi Paolucci Link Board Upgrade Meeting - Dec 2010
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.