Planning and Managing Projects

Similar presentations


Presentation on theme: "Planning and Managing Projects"— Presentation transcript:

1 Planning and Managing Projects
Chapter 8 This presentation covers Chapter 8 – Planning and Managing Projects. The graphic is based on the example used through the Chapter. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 1

2 St. Adolf’s Hospital The next series of slides presents Example 4.1. The series builds in steps to the conclusion of the Example showing the development of key equations along the way. This slide advances automatically. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 9

3 St. Adolf’s Hospital Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. B Select site and do site survey. C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop an information system. J Install the equipment. K Train nurses and support staff. The first step is to create the list of activities and the required predecessors. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 10

4 St. Adolf’s Hospital Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 11

5 St. Adolf’s Hospital AON Network Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Then a network can be drawn. In fact, this step is not strictly necessary for management purposes and large projects are very difficult to represent in this fashion. But it is helpful to visualize this small project in this way. This series builds Figure 4.2. This slide advances automatically. This entire sequence can be automated by selecting automatic advance for each slide and setting the desired delay. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 12

6 St. Adolf’s Hospital AON Network A Immediate
Start A Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

7 St. Adolf’s Hospital AON Network A B Immediate
Start A B Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

8 St. Adolf’s Hospital AON Network A C B Immediate
Start A B C Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

9 St. Adolf’s Hospital AON Network A B C D Immediate
Start A B C D Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

10 St. Adolf’s Hospital AON Network A B C D E Immediate
Start A B C D E Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

11 St. Adolf’s Hospital AON Network A B C D E F Immediate
Start A B C D E F Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

12 St. Adolf’s Hospital AON Network A B C D E F G Immediate
Start A B C D E F G Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

13 St. Adolf’s Hospital AON Network A B C D E F G H Immediate
Start A B C D E F G H Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

14 St. Adolf’s Hospital AON Network A B C D E F G H I Immediate
Start A B C D E F G H I Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

15 St. Adolf’s Hospital AON Network A B C D E F G H I J Immediate
Start A B C D E F G H I J Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

16 St. Adolf’s Hospital AON Network I A F K C G B D H J E Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson AON Network I A F K Start C G B D H J E To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

17 St. Adolf’s Hospital AON Network I A F K C G B D H J E Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson AON Network I A F K Start C G Finish B D H J E Figure 8.4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 24

18 St. Adolf’s Hospital Completion Time Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish We start with the completed project as shown in Figure 4.4. J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

19 St. Adolf’s Hospital Completion Time Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish We can then trace all the possible paths through the project. This sequence is not shown in the text but can be a useful learning tool for students. J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

20 St. Adolf’s Hospital Completion Time Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

21 St. Adolf’s Hospital Completion Time Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

22 St. Adolf’s Hospital Completion Time Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

23 St. Adolf’s Hospital Completion Time Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

24 St. Adolf’s Hospital Path Expected Time (wks) A-F-K 28 A-I-K 33
A-C-G-J 61 B-D-H-J 63 B-E-J 37 Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish The path with the longest time, B-D-H-J-K, is the critical path. J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

25 St. Adolf’s Hospital Path Expected Time (wks) A-F-K 28 A-I-K 33
A-C-G-J 61 B-D-H-J 63 B-E-J 37 Immediate Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish This slide advances automatically. J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

26 St. Adolf’s Hospital Completion Time Immediate
Activity Description Predecessor(s) Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans and layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson Completion Time I 15 F 10 C D E 24 A 12 B 9 K 6 G 35 H 40 Start Finish This slide advances automatically. J 4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 39

27 St. Adolf’s Hospital The next series of slides presents Example 4.2. The series builds in steps to the conclusion of the Example showing the development of key equations along the way. This slide advances automatically. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 44

28 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish We can calculate the earliest possible starting times and earliest possible finishing times for each activity. B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 45

29 St. Adolf’s Hospital Earliest Start and Earliest Finish Times
15 Earliest start time A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 46

30 St. Adolf’s Hospital Earliest Start and Earliest Finish Times
15 Earliest finish time Earliest start time A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 47

31 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 48

32 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish The calculations must proceed through the network after earlier activities are calculated. For example, activity D can not start until activity B is complete. B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 49

33 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 50

34 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 51

35 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 52

36 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 53

37 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Start
15 A 12 F 10 K 6 C 10 G 35 Start Finish In this way ES and EF times can be completed for the entire network. B 9 D 10 H 40 J 4 Earliest Start and Earliest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 54

38 St. Adolf’s Hospital Latest Start and Latest Finish Times Project
15 A 12 F 10 K 6 C 10 G 35 Start Finish In much the same fashion, late start and late finish times can be calculated working backward through the network. This is Example 4.3 in the text. This slide advances automatically. B 9 D 10 H 40 J 4 Project finish Time = 63 Latest Start and Latest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 55

39 St. Adolf’s Hospital Latest Start and Latest Finish Times Latest
15 A 12 F 10 K 6 Latest finish time C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Latest finish time Latest Start and Latest Finish Times 63 E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 56

40 St. Adolf’s Hospital Latest Start and Latest Finish Times Latest start
15 A 12 F 10 Latest start time K 6 Latest finish time C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Latest Start and Latest Finish Times Latest start time E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 57

41 St. Adolf’s Hospital Latest Start and Latest Finish Times Start Finish
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Latest Start and Latest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 58

42 St. Adolf’s Hospital Latest Start and Latest Finish Times Start Finish
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Latest Start and Latest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 59

43 St. Adolf’s Hospital Latest Start and Latest Finish Times Start Finish
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Latest Start and Latest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 60

44 St. Adolf’s Hospital Latest Start and Latest Finish Times
15 Earliest start time Earliest finish time Latest start time Latest finish time A 12 F 10 K 6 C 10 G 35 Start Finish Critical path B 9 D 10 H 40 J 4 Latest Start and Latest Finish Times E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 61

45 St. Adolf’s Hospital Activity Slack Analysis Start Finish I 15 A 12 F
A 12 F 10 K 6 C 10 G 35 Start Finish Having these sets of times it is possible to analyze slack for the network. This starts the presentation of Example 4.4. The series first shows the manual development of activity slack and then presents the screen shot of the Project output, Figure 4.9. This slide advances automatically. B 9 D 10 H 40 J 4 Activity Slack Analysis E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 62

46 St. Adolf’s Hospital Activity Slack Analysis Activity Slack Finish I
15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Activity Slack Analysis E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 68

47 St. Adolf’s Hospital Activity Slack Analysis Activity Slack
15 Slack = LS – ES or Slack = LF – EF A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Activity Slack Analysis E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 68

48 St. Adolf’s Hospital Activity Slack Analysis Activity Slack
15 SlackK = 57 – 27 = 30 or SlackK = 63 – 33 = 30 A 12 F 10 K 6 C 10 G 35 Start Finish Using either the ES/LS or EF/LF pairs results in the same analysis. B 9 D 10 H 40 J 4 Activity Slack Analysis E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 68

49 St. Adolf’s Hospital Activity Slack Analysis Node Duration ES LS Slack
15 A 12 F 10 K 6 C 10 G 35 Start Finish Completing the analysis for the entire network, these are the results. B 9 D 10 H 40 J 4 Activity Slack Analysis E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 68

50 St. Adolf’s Hospital Activity Slack Analysis Node Duration ES LS Slack
B C D E F G H I J K I 15 A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 Activity Slack Analysis E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 68

51 St. Adolf’s Hospital Critical Path Node Duration ES LS Slack
B C D E F G H I J K I 15 F 10 K 6 C 10 G 35 Finish The critical path will be the path with zero slack. B 9 D 10 H 40 J 4 E 24 Critical Path To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 69

52 St. Adolf’s Hospital Critical Path Start Finish I 15 A 12 F 10 K 6 C
A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 Critical Path To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 69

53 St. Adolf’s Hospital Cost-Time Relationships in Cost Analysis 8000 —
7000 — 6000 — 5000 — 4000 — 3000 — 0 — Direct cost (dollars) | | | | | | Time (weeks) Crash cost (CC) Normal cost (NC) Linear cost assumption Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks 5200 This slide advances automatically. (Crash time) (Normal time) Figure 8.11 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 93

54 St. Adolf’s Hospital TABLE 8.1 DIRECT COST AND TIME DATA FOR THE ST. ADOLF’S HOSPITAL PROJECT A 12 $ 12, $ 13,000 1 $ 1,000 B 9 50, , ,000 C 10 4, , D 10 16, , ,000 E , , ,000 F 10 10, , ,500 G , , ,000 H 40 1,200, ,260, ,000 I 15 40, , ,500 J 4 10, , ,000 K 6 30, , ,000 Totals $1,992,000 $2,209,000 Maximum Normal Normal Crash Crash Time Cost of Time Cost Time Cost Reduction Crashing per Activity (NT) (NC) (CT) (CC) (wk) Week This slide presents Table 4.1 with all the necessary cost data. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 94

55 St. Adolf’s Hospital Modeling project schedule in Excel
Forward schedule (Earliest time) ES = EF of predecessor, if only one predecessor ES = Max(EF of predecessors), if more than one EF = ES + Activity duration Backward schedule (Latest time) LF = LS of successor, if only one successor ES = Min(LS of successors), if more than one LS = LF - Activity duration To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.

56 St. Adolf’s Hospital Optimal crashing using Excel Solver
Target cell = Cost or project completion time Changing cells = Crashing time Constraints = Crashing time <= MTR Options: Non-negative Tolerance Estimates, derivative, search To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.

57 St. Adolf’s Hospital Pert = Project Evaluation Review Technique
Finding probability for project completion time To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.

58 Probabilistic Time Estimates
Probability Mean m a b Figure 8.12 (a) Beta Distribution To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 72

59 ( ) St. Adolf’s Hospital te = 2 = Probabilistic Time Estimates Mean
K te = a + 4m + b 6 Mean Start C G Finish B D H J Often referred to as the PERT technique, the use of probabilistic time estimates allows for additional analysis of the project network. 2 = ( ) b – a 6 2 Variance E To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 75

60 St. Adolf’s Hospital Probabilistic Time Estimates Activity B Most
K Activity B Most Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 Start C G Finish B D H J Often referred to as the PERT technique, the use of probabilistic time estimates allows for additional analysis of the project network. E Example 8.6 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 75

61 ( ) St. Adolf’s Hospital te = = 9 weeks 2 = = 1.78
Probabilistic Time Estimates I A F K Activity B Most Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 Start C G Finish B D H J te = = 9 weeks 7 + 4(8) + 15 6 2 = = 1.78 ( ) 15 - 7 2 E Example 8.6 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 77

62 St. Adolf’s Hospital Time Estimates (wk) Activity Statistics
Optimistic Likely Pessimistic Expected Variance Activity (a) (m) (b) Time (te ) (2 ) Time Estimates (wk) Activity Statistics A B C D E F G H I J K This table shows all the expected task times and variances for use in the probabilistic calculations. Example 8.6 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 79

63 St. Adolf’s Hospital 2 =  (variances of critical path activities)
What is the probability the project will be completed in 65 weeks? Critical Path = B - D - H - J TE = = 63 weeks 2 =  (variances of critical path activities) This slide advances automatically. 2 = = 11.78  = = 3.432 Example 8.7 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 83

64 St. Adolf’s Hospital T – TE  Probabilities
Critical Path = B - D - H - J T = 65 days TE = 63 days s = 3.432 T – TE 65 – 63 3.432 z = = = 0.58 From Normal table in page 807, for z = 0.58, the table area = The probability that the project will be Completed within 65 days is 71.9% Example 8.7 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.

65 St. Adolf’s Hospital Normal distribution: Mean = 63 weeks;
Probability of meeting the schedule is Length of critical path Probability of exceeding 65 weeks is 63 65 Project duration (weeks) To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.

66 St. Adolf’s Hospital T = 63 + 2.055 (3.432) = 70.05 weeks
Expected project completion time with 98% probability Critical Path = B - D - H - J T = TE + z s Normal table for 98%, z = 2.055 T = (3.432) = weeks To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.

67 St. Adolf’s Hospital 2 =  (variances of activities)
Probabilities Path = A - C - G – J Find probability for T = 65 days TE = = 61 days 2 =  (variances of activities) 2 = = 15.44 z = T – TE 2 z = = 1.02 65 – 61 15.44 From Appendix 2 Pz = .8461 Example 8.7 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.