South Eastern University of Sri Lanka
Progress Report on Construction Projects / Development Projects as at 31st July 2015
2
Building Complex for Main Library
Total Cost Estimate : 200 Million Physical Progress : 100% Financial Progress : %
3
Building Complex for the Faculty of Management & Commerce
Total Cost Estimate : 160 Million Physical Progress : 100% Financial Progress : 95.74%
4
Building Complex for Faculty of Applied Sciences at Sammanthurai
Total Cost Estimate : 170 Million Physical Progress : 100% Financial Progress : 80.08%
5
Building Complex for Student Hostel & Staff Quarters at Sammanthurai
Total Cost Estimate : 149 Million Physical Progress : 85% Financial Progress : 47.02%