Fresno County Rural Transit Agency Moses Stites General Manager
If I Could Turn Back Time: A Small Agency ZEB Procurement Panel April 24th, 2019 Fresno County Rural Transit Agency Moses Stites General Manager
2
FCRTA Service Area Serving 13 incorporated and 29 unincorporated communities in Fresno County
3
FCRTA Current Fleet Vehicle fleet of one hundred and ten (110) vehicles Forty-four (44) are powered by CNG Twenty-three (23) are powered by electric batteries FCRTA does not operate any diesel powered vehicles Goal of 2025 to have 100% alternative fuel fleet
4
FCRTA’s Electric Fleet
(2) 35ft BYD Electric Buses (5) 40ft Proterra Electric Buses (6) Electric Zenith Vans (10) Chevy Bolt Sedans
5
FCRTA’s Charging Infrastructure
4. 1. Envision Solar Arc 2. Proterra Charger (Level 3) 3. JuiceBox Charger (Level 2) 4. BYD Charger (Level 2) 3. 1. 2.
6
Challenges & Lessons Learned with ZEB’s
Charging infrastructure installation is costly and takes time Extra driver training is required for electric vehicles Range is a big factor for operating on rural routes with high mileage W/C Lifts in some manufacturers has been problematic ADA accessibility (sedans vs. other vehicles) There is driver training offered by the manufacturer, contact FCRTA is you would like this information.
7
Charging Infrastructure Installation Costs
8