1
Shut 95SS2-235 (245)
2
IF draining to Recovery Header,
THEN check SHUT 95SS2-238 (248) AND
3
IF draining to Recovery Header,
THEN check SHUT 95SS2-238 (248) AND check OPEN 95SS2-237 (247)
4
IF draining to Drain Header ,
THEN check SHUT 95SS2-237 (247) AND
5
IF draining to Drain Header ,
THEN check SHUT 95SS2-237 (247) AND check OPEN 95SS2-238 (248)
6
Check OPEN 95SS2-234 (244) AND 95SS2-236 (246)
7
Check SHUT V1 (V2) on jumper
8
Insert jumper into test connections for A (B) Hotwell Conductivity cell.
9
Jumper Installation Sign Attachment 11 as installer.
Have a second person verify proper installation AND sign Attachment 11 as verifier.
10
Throttle OPEN V1 (V2) to obtain about 100 cc/min on 95FI-118 (120).
11
Hang tag on installed jumper identifying PC-02
Hang tag on installed jumper identifying PC as installation procedure