Energy Retrofit Project Oxford Hills School District March 18, 2019
Phase 5 - a Energy Retrofit Project Oxford Hills School District March 18, 2019
2
Project Summary OHCHS Roof & HVAC Replacement
Guy E. Rowe HVAC Upgrades Otisfield Community School – Roof Lighting Retrofits Harrison Elementary School, Paris Elementary School, Guy E. Rowe School
3
OHCHS Roof Replace entire roof Replace 3 of 9 HVAC Rooftop Units
178,484 square feet 20+ years old Rapidly deteriorating Replace 3 of 9 HVAC Rooftop Units Cost $2,397,470 Cost split with MVR #11 60% District 40% MVR #11
4
Guy E. Rowe School HVAC Upgrade Lighting Retrofit Hallways
Includes Air Conditioning in all Classrooms Lighting Retrofit Hallways Cost $1,759,834
5
Otisfield Community School
Replace entire roof 29 Years Old Cost $586,878
6
Other Buildings Harrison Elementary School Lighting Retrofit $55,279
Paris Elementary School Lighting Retrofit $128,187 Lower payback improves the cashflow of entire project
7
Budget OHCHS Roof $2,397,470 Guy E. Rowe HVAC $1,759,034
SAD 17 Portion $1,438,482 Guy E. Rowe HVAC $1,759,034 Otisfield Roof $586,878 Lighting Retrofits $220,935 Engineering and Other Fees $315,109 Total Phase 5-a $5,279,426 Financed through a Performance Contract – 15 Year Loan Interest only payment in FY 20 Estimated cost year 1, $73,800 Estimated cost year 2, $399,340 Vocational school will need to budget for 40% of the payment on high school portion of the project, (18% of the total cost)
8
Phase 5-b and Phase 5-c OHCHS Replace HVAC Units 4 – 9
Replace Walk-in Coolers - Food Service and Culinary Arts Central Office Siemens EMS Conversion District Wide Siemens Automation Upgrade Replace panels at each school
9
Time-Line March 18 Board action on project and financing March 20
Sign Contracts April 1 - Work begins on OHCHS Roof (30 week project) On-going - Operations Committee and Administration continue to work on Phase 5-b and Phase 5-c Siemens Automation Upgrade Replace panels at each school