Download presentation
Presentation is loading. Please wait.
1
LCLS Injector Commissioning P
LCLS Injector Commissioning P. Emma, for the LCLS Commissioning Team LCLS DOE Review July 10, 2007 LCLS
2
LCLS Injector Layout 6 MeV 135 MeV 250 MeV OTR screens (7)
YAG screens (7) RF Gun Wire scanners (7) Dipole magnets (8) Beam stoppers (2) L0a S-band RF acc. sections (5) Gun Spectrometer L0b Emittance Screens/Wires Emittance Screen/Wires RF Deflector 2-km point in 3-km SLAC linac L1S X-band RF acc. section 135-MeV Spectrometer BC1 TD11 stopper 135 MeV 250 MeV (not to scale)
3
Electron Beam Transported to All Areas
April 5: First e- from gun (6 MeV) April 5: First e- to gun spectrometer (6 MeV) April 8: First e- to inj-spectrometer (135 MeV) April 14: First e- through BC1 (250 MeV) June 20: First e- through main linac (16 GeV)
4
Parameters and Highlights
Up to 500 pC of charge (500 µJ laser energy) 10 Hz beam & 30 Hz RF (30 Hz e- also tested) RF Gun is quite reliable and performing well Transverse RF deflector working (×2) X-band RF (4th harmonic) up and running Emittance diagnostics (OTR + wires) and software working very well (gex,y nC) Bunch compression & possible COTR observed RF feedback systems operational Commissioning ends Sep. 4 (BC2 starts Dec. ‘07)
5
Pre-Beam Tunnel Check List Complete
40 pages, ~2000 checks – all DONE Polarity conventions Field type (quad, dipole) Serial numbers Installation orientation etc. etc.
6
RF Gun Installed in March 2007
D. Dowell breakout
7
e- e- Q 0.5 nC fRF = 30 Hz G 110 MV/m gex,y 1.2 mm DtFW 6.5 ps
Ipk 75 A E 5.8 MeV QE 1×10-5 spec. dipole e- UV laser YAG screens solenoid Cathode (Cu) Dual RF feed RF gun
8
Laser Spatial and Temporal Shaping
R = 0.7 mm 7.1 ps Spatial shape on cathode using iris Temporal shape (7.1 ps FWHM) Good up time and energy on cathode above spec .(500 μJ) W. White breakout
9
Beam on YAG02 Screen (80 cm from gun)
First electron beam on April 5, 2007 20 mm
10
Injector Trajectory (BPMs) – Good Alignment
11
EPICS Controls - Vacuum
H. Shoaee
12
EPICS Controls - Magnets
13
Emittance Measurements with Quad-Scans and with Multiple Profile Monitors (OTR & Wire-Scanners)
H. Loos breakout Q 450 pC gex = 0.91 μm quad scan
14
Repetitive Emittance Measurements
15
Transverse RF Deflector as Diagnostic
RF deflector OFF RF deflector ON RF deflector ON head high E tail Screen image with RF deflector OFF (left) and ON (middle), for measuring sliced emittance. A 2nd screen after a bend (right), with deflector ON, shows longitudinal phase space.
16
Measured Temporal Distribution of Bunch
Temporal distribution of e- beam measured with the transverse RF deflector upstream of BC1.
17
Time-sliced Emittance Measured Routinely
gex ~1 ps C. Limborg breakout Time-sliced x-emittance measured on pre-BC1 OTR screen using quad-scan at 0.2 nC and 0.7-mm cathode spot radius. Each slice is about 1 ps wide.
18
motor controlled translation stage
X-Band RF (11.4 GHz) and BC1 Chicane are Fully Operational BPM for energy feedback (20 mm resolution) Offset: 0 to 26 cm (23 cm nominal) collimator BPM tweaker quadrupoles OTR screen motor controlled translation stage J. Frisch breakout RF deflector OFF RF deflector ON Deflector ON & X-band ON X-band correction energy chirp only
19
Residual Dispersion Measurements & Correction
BPM Scan energy… BPM B2 B3 BPM BPM B1 B4 S-band acc. CQ11 CQ12 Read BPMs… …set quads BC1 Assumes e0 = 1 μm & sd = 1.6% Before correction After CQ11/CQ12 correction
20
BC1 Dipole Field Quality Poor
quads use to correct ‘CQ’ quads off nominal x-position dipoles need work
21
Bunch Compression Observed with CER
L1S-linac RF phase: j = 0º j = 15º j = 20º j = 25º j = 30º j = 35º j = 40º Coherent edge radiation (CER) detector after BC1
22
Hor. emittance growth in X-band RF
L1S X-band RF acc. section BC1 stopper gex Dx = 1.2 mm gey ~65 μrad pk (1.3 keV) X-band RF ON X-band RF OFF x kick at downstream BPM
23
Transverse Wakefield in X-Band Structure
Q 500 pC BC1 OFF X-band RF OFF gex (μm) Dx = +0.6 mm
24
LCLS Beam Down SLAC Linac with 500 pC and up to 16 GeV
end of linac screen 1 km
25
2007 Injector Commissioning Goals
DONE DONE DONE DONE ~DONE DONE CONTINUES STARTED
26
LCLS Installation and Commissioning Time-Line
June 29, 2007 linac/BC2 Install LTU/Und/Dump FEE/NEH Install First Spont. Light X-Ray tunnel/FEH Install now CD-4a J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 2007 2008 2009 PPS PPS Controls checkout & re-commission injector Re-commission Inj/BC2 to SL2 …Injector Commissioning Linac/BC2 Commissioning LTU/Und/FEE Commissioning FEL Commissioning
27
Problems/Issues Gun Faraday cup & toroid not functioning
BC1 motion control limited (300 mm 260 mm) Cathode QE 3-10 times below design (improving!) Some controls tools late (orbit displays, fitting, magnet control & alarms) Laser phase drift and lock trouble until mid-June Hor. emittance growth from X-band RF (?) BC1 dipole field quality poor
28
Summary Beam transported to all areas (no major problems)
No obstructions or ‘backwards’ components (except laser alignment mirror) BC1 & X-band emittance preservation problems Controls still developing, but working well and improving fast – great cooperation and effort Matlab control tools are indispensable Communication with laser group excellent BC2/Linac commissioning starts in Dec. ’07 GREAT commissioning team! (see breakout talks) Thanks to all – results are quite positive (in spite of my constant whining)
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.