Estimating the Cost for the Concrete Pad
Civil Engineering and Architecture Unit 2 – Lesson 2.2 – Cost and Efficiency Analysis Estimating the Cost for the Concrete Pad Project Lead The Way, Inc. Copyright 2010
2
How Much Will the Concrete Cost?
Estimating the Cost for the Concrete Pad Civil Engineering and Architecture Unit 2 – Lesson 2.2 – Cost and Efficiency Analysis How Much Will the Concrete Cost? Concrete is sold by volume and measured in cubic yards (yd3) Concrete is typically sold in increments of ½ yd3 Example: $98/ yard3 x 4.0 yards3 = $392 Project Lead The Way, Inc. Copyright 2010
3
Determine Footprint of Pad in yd3
Estimating the Cost for the Concrete Pad Civil Engineering and Architecture Unit 2 – Lesson 2.2 – Cost and Efficiency Analysis Determine Footprint of Pad in yd3 Pad size = 16 ft x 18 ft floor , 4 in. thick Convert all units to ft 16 ft, 18 ft, .333 ft Calculate volume (L x W x t) Convert ft3 to yd3 (1 ft = 12 in.) Project Lead The Way, Inc. Copyright 2010
4
Guidelines for Estimating Rebar Quantity
Estimating the Cost for the Concrete Pad Civil Engineering and Architecture Unit 2 – Lesson 2.2 – Cost and Efficiency Analysis Guidelines for Estimating Rebar Quantity Placed every two feet (max.) on a grid Sold in various lengths Must be lapped 6 in. to maintain strength Maintain a 3 in. edge distance 6 in. lap 3 in. edge dist. Project Lead The Way, Inc. Copyright 2010
5
Example: Estimate how many 10 ft pieces of rebar are needed?
Estimating the Cost for the Concrete Pad Civil Engineering and Architecture Unit 2 – Lesson 2.2 – Cost and Efficiency Analysis Example: Estimate how many 10 ft pieces of rebar are needed? 6 in. lap 3 in. edge dist. [After the question is displayed, give students a chance to estimate the number of 10 ft pieces necessary. Then click to show the answer.] You will need nineteen full 10 ft pieces, plus nine 10 ft bars from which you will cut the 8 ft pieces. You will also need ft bars from which to cut the 6 ft pieces. Order a total of 38 (= ) 10 ft pieces. Project Lead The Way, Inc. Copyright 2010
6
Answer: You will need to 38 10’ pieces of rebar
Estimating the Cost for the Concrete Pad Civil Engineering and Architecture Unit 2 – Lesson 2.2 – Cost and Efficiency Analysis Answer: You will need to 38 10’ pieces of rebar Breakdown: 3 in. edge dist. 6 in. lap [After the question is displayed, give students a chance to estimate the number of 10 ft pieces necessary. Then click to show the answer.] You will need nineteen full 10 ft pieces, plus nine 10 ft bars from which you will cut the 8 ft pieces. You will also need ft bars from which to cut the 6 ft pieces. Order a total of 38 (= ) 10 ft pieces. Project Lead The Way, Inc. Copyright 2010
7
Estimating the Total Cost of the Pad
Estimating the Cost for the Concrete Pad Civil Engineering and Architecture Unit 2 – Lesson 2.2 – Cost and Efficiency Analysis Estimating the Total Cost of the Pad Rebar Each piece of #4 rebar costs $4.78. 38 x $4.78 = $181.64 Other associated costs include material for forms, gravel, and labor. Project Lead The Way, Inc. Copyright 2010