Presentation is loading. Please wait.

Presentation is loading. Please wait.

Maryland Offshore Windfarm Project

Similar presentations


Presentation on theme: "Maryland Offshore Windfarm Project"— Presentation transcript:

1 Maryland Offshore Windfarm Project
January 2018

2 1. Maryland Offshore Wind Project Description

3 Federal lease Area of MARYLAND WIND ENERGY AREA (WEA) 80,000 Acres Enough for 1,500MW of Wind Power

4 Current US Wind Project: 86 Turbine installations 722.4 MW of Power

5 Turbine Layout

6

7 US Wind, Inc.- Maryland Project
Project Description: 12-Miles off of Ocean City, MD Applying for 750MW with PJM ~260MW will use Maryland OREC 86 Total Turbine Installations In-Service Date of 2021

8 2. Maryland Project Development Status

9 US Wind, Inc, Activities Since Lease
2015 Leased Office in Downtown Baltimore- Began Staffing Project Development Team Carried out FEED Studies for Cable and Foundations Carried out Geo-Phys and Geo-Tech Surveys in WEA PJM Process Commenced Site Assessment Plan Submitted to BOEM

10 US Wind, Inc, Activities Since Lease
(cont.) OREC Application Process Resulted in OREC Award for 913,000 MWh/yr Cable Easement Survey First Phase in 2016 Second Phase completed late 2017 (included re-route in IRB to avoid high density clam areas)

11 IRB Re-Route

12 IRB Re-Route

13 US Wind, Inc, 2018 Activities SAP Approval and Installation of Met Tower Construction and Operations Plan Submittal

14 OSW Project Timeline CONSTRUCTION PHASE
-Foundation Installation start: 2019 -Construction finish: 2020 -In-service (COD): 2021 OPERATION & MAINTENANCE (O&M) PHASE -Begin O&M Operations: 2021 -Finalize O&M: Q4 2045 -Decommissioning Plant: 2046

15 Atlantic Wind Connection - Monmouth County Informational Meeting
07/29/2011 1 North Charles Street, Suite 2310 Baltimore, MD 21201 Jen Banks Permitting Specialist (919)


Download ppt "Maryland Offshore Windfarm Project"

Similar presentations


Ads by Google