Lafayette New Terminal Program Update
September 12, 2018
3
Terminal Program Update
FAA Grant Application Submitted & Offers Have Been Issued 2018 Federal Grant Amount: $21,787,704 Waiting on AIP Supplemental Discretionary Application PFC Application is Under FAA Review Approved Draft of CIP LA DOTD Terminal Program Update
4
Terminal Program Update
LA FP&C Capital Outlay Bonding Commission accepted $1.7 million Approved Utilization of Funds for QTA Waiting on Cooperative Agreement to be Finalized EDA Grant Application Waiting to receive feedback TSA OTA Application Submitted Grant Application, Waiting on Feedback
5
Terminal Program Update
Airlines Airlines Approved Terminal Design to Date QTA Continued to Meet with Rental Car Companies, Moving Forward on QTA Lease Rates Short Term Financing Conversations On Going
6
Terminal Program Update
QTA Timeline: Sept ‘18: Commission to Approve Updated CFC Oct. ‘18: Commission to Approve Short Term Finance Nov. ‘18: Construction Bids Due (Pending FP&C Approvals) Dec. ‘18: Notice to Proceed Oct. ‘19: Construction Complete Terminal Program Update
7
Terminal Program Update
Enabling Demo Kickoff August 30th Terminal Program Update
8
Terminal Program Update
Enabling Demo AOA Barrier & Temporary Fencing Complete Interior Abatement of Old Hangar Complete Demo is Proceeding Terminal Program Update
9
Terminal Program Update
Enabling Demo Terminal Program Update
10
Terminal Program Update
GMP 1: Subcontractor Bidding Completed Final Amendment Will Be Submitted at Next Commission Meeting Schedule Starts: Oct. ‘18: RTR Relocation Nov. ‘18: RTR Facility Construction Jan. ‘18: Terminal Foundation Construction GMP 2: Structural Steel Construction December 2018 Approval GMP 3 100% Design is on Schedule in January April 2019 Approval Terminal Program Update