1 Multi-discipline academic research science technology engineering & math (stem) building project phase 1 NAU Project No RFQ for Construction Risk, Pre-Construction Services for Programming Pre-Submittal Conference Tuesday, March 26, 2019 at 12:00 PM

2 Team Introductions Judith Scholar Winfield – Primary RFQ contact
Kelly Davis – Project Manager Andrew Iacona – Project Manager Steve Vedral – Director of PDC/AVP of Facility Services Dr. Dan Okoli – VP of Capital Planning and Campus Operations Executive Steering Committee

3 Project Program Multi-Discipline Research and Academic Building Dedicated to STEM Programs Pre-construction services for programming At completion of programming NAU may request a proposal to continue services through construction with experience in construction of similar projects in a higher education environment. will be part of a team that will work together in a cooperative and mutually supportive manner for the benefit of The Project • Phase 1 of two-phase program

4

5 Preliminary Project Schedule
Final Programming Package: TBD Design / Preconstruction Fall 2019 Demolish Peterson (Building #22) Summer 2020 Commence Construction Summer 2021 Substantial Completion Spring 2023 Building Occupancy September 2023

6 procurement dates: Pre-Submittal Conference: March 26, 2019, 12:00 PM (local) Deadline for Inquiries: April 5, 2019, 2:00 PM Qualifications Due: April 12, 2019, 2:00 PM Shortlist Firm Interviews: May 6, 2019 (Tentative) (Optional) Begin Contract Period: May 2019

7 Qualifications Submittal Info
Partnering arrangements Disqualification items Submission location and delivery via FedEx, USPS, or UPS

8 Additional Pertinent Items
The selected CMAR Firm shall be responsible to be familiar with the University’s current CMAR contract. The selected firm will also need to make themselves familiar with the University’s current University Design Guidelines and Technical Standards. Current versions for all of the documents mentioned above can be found at:

9 QuestiONS