1 SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 06/03/2019

2 Helium line Helium line coming from BA6 to BA4
This line is NOT OBSOLETE It will be out of service un the coming days until beginning of 2020 It will be displaced under the blue walkway 06/03/2019 J.MEIGNAN

3 Hole in LSS5: can we fill it?
06/03/2019 J.MEIGNAN

4 Reminder: rules near BA5
To avoid problems seen during other YETS/EYETS with neighbours Road to use Pedestrian roads Parking outside point 5 : forbidden 06/03/2019 J.MEIGNAN

5 Self rescue masks Must be with you in the tunnel
Tolerance: can be put down in a small perimeter around you (“à portée de main”) 06/03/2019 J.MEIGNAN

6 Activities ongoing week 9/10
Point 1 BA1: Transformer maintenance Toilet renovation Chilled water connection to BM1 LSS1-/Arc1-: Safety cable trays Shaft/TA/TT10: Fire safety WP3 (Dry riser): TT10 OK, TA/shaft almost finished Smoothing survey ongoing 06/03/2019 J.MEIGNAN

7 Activities ongoing week 9-10
Point 5 BA5: Decabling (also in TA/Shaft) Power converters reconfiguration Shaft/TA Underground toilet block removal (?) LSS5 Decabling campaign Transmission line installation 06/03/2019 J.MEIGNAN

8 Activities ongoing week 9-10
Point 5 ECX5 Moving of the cable trays in the tunnel eye Arc 5+: Fire safety WP3 (fire safety) BB5: Mock up ongoing (and impressive!) 06/03/2019 J.MEIGNAN

9 Activities scheduled on week 10
Point 1: Lift maintenance 11/03/2019 (6a.m to 8 a.m) Lift reparation (cordelette): 1 day without lift the 19/03/2019 Point 5: BA5 Power converters reconfiguration LSS5 Decabling campaign Transmission line installation ECX5 Moving of the Helium line and fire detection tubes 06/03/2019 J.MEIGNAN

10 Any questions?

11 **Supports Equipment owners are responsible of their supports
They are in charge to organise their removal, packaging and storage EN-HE will transport these supports to the storage place 06/03/2019 J.MEIGNAN