1 Dynamics and Risks of KenGen Portfolio Revenue Budgeting
JOH-KGN JvW-X1 Dynamics and Risks of KenGen Portfolio Revenue Budgeting Freda Nyambura Engineer II – Technical Affairs 2018 G2G INNOVATION SEMINAR, PRIDEINN PARADISE 18TH JUNE - 22ND JUNE 2018

2 FREDA NYAMBURA Engineer II – Technical Affairs Qualifications:
JOH-KGN JvW-X1 FREDA NYAMBURA Engineer II – Technical Affairs Qualifications: Currently pursuing a Masters in Public Policy Analysis BSc. Energy Engineering Responsibilities: Her main focus is development, implementation and monitoring for the PPAs across the company. Key milestones/achievements include: Conducted the PPA tests for the 280 MW project Part of the project team for the billing efficiency initiative between KenGen and KPLC A member of the Association of Energy Engineers.

3 Introduction

4 Vehicle Power Plant Capacity Cc MW Charge Mileage payment Energy payment Availability Percentage of the time that I can comfortably have my car ready to be driven after taking out maintenance time. Percentage of the time that the plant can comfortably be ready to generate after taking out maintenance time. Load factor The ratio of the actual mileage to the possible mileage in a given time period. The ratio of the actual energy generated to the possible actual generation in a certain time period

5 The focus of this presentation is the load factor
The focus of this presentation is the load factor. The load factor is one of the negotiated items during the PPAs negotiations. The load factor affects the energy revenue.

6 Kipevu III PPA load factor Budget load factor Actual load factor 30.00 66.54 52.04 32.30 29.68 13.30 17.96 20.00 50.84

7 The value of the gain in load factor in the FY 2016-17 was Kshs
The value of the gain in load factor in the FY was Kshs. 173 Million.

8 Olkaria IV PPA load factor Budget Load factor Actual load factor 85.00 88.41 86.77 85.26 79.33 90.00 69.50

9 The value of the lost load factor for the FY 2016-17 is Kshs. 189
The value of the lost load factor for the FY is Kshs Million

10 Sagana PPA load factor Budget Load factor Actual load factor 70.00 83.47 68.88 62.22 57.45 59.49 57.85 59.37 31.82

11 The value of the lost load factor for thr FY is Kshs. 39.04 Million

12 Gitaru PPA load factor Budget Load factor Actual load factor 54.00 44.70 43.86 54.73 37.52 39.36 45.56 38.31 40.97

13 The value of the lost load factor in the FY 2016-17 is Kshs. 7
The value of the lost load factor in the FY is Kshs Million.

14 Major Hydro PPA load factor Budget Load factor Actual load factor 54.00 50.14 56.32 46.62 46.59 47.17 53.28 45.33 47.81

15 The value of the load load factor in the FY 2016-17 is Kshs. 12
The value of the load load factor in the FY is Kshs Million

16 Way forward and Conclusion
The annual budgeting load factor is a moving number while the PPA load factor is a locked number for the lifetime of the plant. Moving forward, my suggestion is that we have the PPA load factor as the in-house KPI load factor and the annual load factor as the load factor for that will factor in any maintenance we may have in the given year.