ABP/RTL Main RTL Activities for 2007/8:-

Similar presentations


Presentation on theme: "ABP/RTL Main RTL Activities for 2007/8:-"— Presentation transcript:

1 ABP/RTL Main RTL Activities for 2007/8:-
Shutdown Co-ordination and Planning for PSB, PS, LEIR, TT2, AD, SPS, TT40 & TI8 CTF3 and CLEX installation 3 MeV test stand installation LHC Installation (Including TI2) Preparation for LINAC4 construction AB Consolidation project TSO support for accelerators and service buildings 1/6/2007 ABP group meeting

2 ABP/RTL Simon Baird Section Leader & AB Consolidation Raymond Brown PS
Sven De Man PSB & LHC Installation Nicolas Gilbert SPS, TT40, TI2 & TI8 Christian Lacroix LEIR, TT2, AD & 3MeV test stand José Monteiro CTF3, CLEX* & Planning support Bernard Pires SPS Surface buildings  Rosario Principe PS, 3MeV test stand & LINAC4 Michel Samson SPS, TI2 installation, AB Space Management for ADM * (CLIC Experimental Area) 1/6/2007 ABP group meeting

3 Shutdown/Installation Co-ordination
8 PS main magnets renovated & re-installed Some MTE preparatory work was completed but the main MTE work will still take place in the 2007/8 shutdown 76 SPS main magnet water manifolds repaired INB cable loop installed at the SPS Major tunnel repairs in TT2 New beam stopper in BTP line PSB main magnet water cooling renovation CTF3 Combiner ring ejection line completed CLEX building completed (June 07) 1/6/2007 ABP group meeting

4 Shutdown/Installation Co-ordination
2007/8 Shutdown (Minimum length = 12 weeks) MTE installation Essential for full CNGS beam operation PS Main magnet renovation (8 units?) SPS main magnet manifold repairs (80 planned) Move 8 PSB wire scanners? 3MeV test stand installation CTF Installation of CLEX equipment Installation of the TL2 line (from the Combiner Ring to the CLEX) LINAC4 Choice of site Technical coordination for the project 1/6/2007 ABP group meeting

5 TSO’s for Accelerators and the Service Buildings LHC activities
AB Consolidation There are 44 active Work Units in 2007 By the end of a total of 36.8 MCHF will/should have been spent (total budget at present is 50 MCHF ) A full review of all outstanding Consolidation items has been completed:- White Paper request for 27 MCHF & 70 FTE’s Waiting for the “green light” TSO’s for Accelerators and the Service Buildings LHC activities One RTL section member is detached (60%) to TS for the Coordination of LHC installation activities TI2 installation and commissioning coordination No decision on “How an LHC shutdown will be managed” 1/6/2007 ABP group meeting


Download ppt "ABP/RTL Main RTL Activities for 2007/8:-"