19-April-05 Peripheral Crate Testing, Installation, and Commissioning PC I&C Feb ’06 EMU Fred Borcherding 16-May-19 PC I&C Feb'06.

Similar presentations


Presentation on theme: "19-April-05 Peripheral Crate Testing, Installation, and Commissioning PC I&C Feb ’06 EMU Fred Borcherding 16-May-19 PC I&C Feb'06."— Presentation transcript:

1 19-April-05 Peripheral Crate Testing, Installation, and Commissioning PC I&C Feb ’06 EMU Fred Borcherding 16-May-19 PC I&C Feb'06

2 I&C On hand DMB, MPC, CCB, Crates, CRB OSU CC BP TMB/RAT
19-April-05 I&C On hand DMB, MPC, CCB, Crates, CRB Most of inventory is at CERN OSU CC 5 at CERN, more soon BP 11 at CERN installed in PC with ALL hardware 18 more 15-March 15/2wks from then on TMB/RAT 10 of each – pre-production, have been here TMB – 20 next week RAT – 20 in ~1-2 weeks 16-May-19 PC I&C Feb'06

3 19-April-05 I&C (2) PC PC 2 in slice test with pre-production BP – will stay 2 in SX5 in bottom PC racks 4 in B904 ready for board testing 5 in ISR waiting CRB Have made final hose specifications 12 tested and have all hardware attached including hoses Installed in above crates PCMB Many dumb PCMB’s for B904, MTCC etc 2 prototypes for R&D work 4 pre-production being assembled - ~3 weeks Production in beginning stages 16-May-19 PC I&C Feb'06

4 I&C (3) Racks Preparing Racks Installing Racks
19-April-05 I&C (3) Racks Preparing Racks Drawings showing layout of all PC racks have been produced Scroll down on page and pick – ‘Documentation’ > ‘PC rack layout …’ Prep of mini racks has begun at SX5 Installing Racks Top racks will be installed with crane after FULL prep – including PC’s without any boards, +&- Bottom racks on YE+-3 are in and have (+) been will be (-) prep’ed in place Other bottom racks will be install and then prep’ed, but will be last worked on (NOTE – they are removed again when disk lowered) Tall racks on platforms will be installed and then prep’ed Will install and prep ALL (EMU) tall racks 16-May-19 PC I&C Feb'06

5 19-April-05 Software Hyper-DAQ Shell ready, tested, ongoing additions and enhancements Test routines include Tests and programming of individual boards From builders – mostly finished Tests of two or more boards Also involve some ‘calibrations’ – many finished Fast site type tests & calibrations In process Test db All test information saved in files – listing and summary db to be built Basic test unit/run is Test session – finite time interval Particular crate with fixed board load Any board switches require the start of new test run 16-May-19 PC I&C Feb'06

6 LVPS for PC&CSC Maraton for YE+2 Est. complete 15-March
19-April-05 LVPS for PC&CSC Maraton for YE+2 Maraton ready to install at SX5 Need CANBus from GB to YE+2 rack Need to install LV cables for PC’s – will use CSC LV type cable Need to install splitters for CSC Need to specify and make output bus bars and cables from Maraton to splitters Est. complete 15-March 16-May-19 PC I&C Feb'06

7 LVPS for PC&CSC Maraton for YE+3 ??? However Has 1 PC and 3 CSC’s
19-April-05 LVPS for PC&CSC Maraton for YE+3 ??? Has 1 PC and 3 CSC’s Maraton has 4 of 6 outputs available (if gang PC outputs for YE+2) 2 for PC 2 for 3 CSC’s However Longer LV cable runs Special one time setup Needs more investigation 16-May-19 PC I&C Feb'06

8 LVPS for PC&CSC CAEN for YE+1 Est. temporary ready 15-March
19-April-05 LVPS for PC&CSC CAEN for YE+1 Do not have yet Can use temporary supplies until MTCC starts Need CANBus from GB to YE+1 rack Need to understand, specify and install cables from CAEN to PC’s Need to install splitters for CSC Need to specify and make cables from CAEN to splitters Est. temporary ready 15-March 16-May-19 PC I&C Feb'06

9 MTCC CANBus Have 4(5) field buses on detector
19-April-05 MTCC CANBus Have 4(5) field buses on detector Gas Will take separate route to GB CAEN LVPS for PC and CSC Maraton LVPS for PC and CSC PCMB on CRB’s for PC’s Others? Don’t know if they are compatible Can they be combined on single bus? Time is short for thorough tests CAEN will be late Set up maximal system 4 separate long cable runs from GB to YE+1 PP 3 known buses above plus a spare Loop runs from YE+1 PP and back so that can combine or separate buses at will from this point 16-May-19 PC I&C Feb'06

10 MTCC CANBus Long Run CANBus for MTCC CAEN connects inside this rack
19-April-05 MTCC CANBus Long Run CANBus for MTCC Green Barrack to YE+1 tower outside PP YE+1 outside PP to YE+1 inside PP CAEN connects inside this rack GB 16-May-19 PC I&C Feb'06

11 MTCC CANBus Loop allows us to put in series with other buses PCMB bus
19-April-05 MTCC CANBus Loop allows us to put in series with other buses Signal and Power to and back minimizes ground loops PCMB bus requires external 12V PCMB bus PP YE+1 to PC on YE+1 and back PP YE+1 to PP YE+2 and back PP YE+2 to PC on YE+2 and back Optionally PP YE+2 to PP YE+3 and back PP YE+3 to PC on YE+3 and back 16-May-19 PC I&C Feb'06

12 MTCC CANBus Maraton bus PP YE+1 to PP YE+2 and back
19-April-05 MTCC CANBus Maraton bus PP YE+1 to PP YE+2 and back PP YE+2 to Maratons and back 16-May-19 PC I&C Feb'06

13 Summary Working on Racks and crates Working on infrastructure for MTCC
19-April-05 Summary Working on Racks and crates Working on infrastructure for MTCC Eager to begin I&C Visit I&C web site at 16-May-19 PC I&C Feb'06