Transmission Service Requests Overview
2008 Transmission Summit July 29, 2008 New Orleans, LA
3
ICT TSR Responsibilities
Maintain, Administer, and Post for Long-Term Transmission Service Requests Long-term service requests (≥1 year) or requests outside the Study Horizon (18 months) Schedule, send, receive, and validate all Study Agreements System Impact Study Agreement (SISA) Facilities Study Agreement (FSA) Affected System Agreements Respond to any inquiries by the Transmission Service Customer via phone, , and IssueTrak.
4
ICT TSR Responsibilities
Perform System Impact Study Post all study reports (SISR & FSR) and documentation as per Entergy’s Tariff Provide all notices to the customer as required
5
ICT TSR Responsibilities
Review and validate the results of the Facilities Study Classify upgrades as Base Plan or Supplemental as per Attachment T of Entergy’s Tariff Coordinate studies with any Affected Systems
6
Entergy TSR Responsibilities
Review System Impact Study Report (SISR) Tender, enter into, and file all Transmission Service Agreements Enter into 3rd party Facilities Study Agreement (FSA) with ICT and Customer Perform Facilities Study
7
Transmission Service Requests (Since 2007 Summit)
ICT has sent out 248 SISAs ICT has performed and posted 154 SISRs on time ICT has 17 SIS in process Entergy has performed 48 FSRs on time Entergy has 5 FS in process
8
System Impact Studies ICT has performed and posted 154 SISRs
53 Point to Point Requests 9 Monthly Requests 101 Network Requests 4 Monthly Requests 3 Affected System Requests ICT has 17 SIS in process 2 Monthly Firm PTP 1 Monthly Network 6 Long Term Firm PTP 3 Long Term Network 5 Affected System
9
Facilities Studies Entergy has performed 48 FSRs
14 Point to Point Requests 13 Long Term Firm Requests 1 Affected System Request 34 Network Requests 31 Yearly Network Requests 3 Affected System Requests Entergy has 5 FS in progress 5 Yearly Network Requests
10
James Lyle 501-614-3561 JLyle@SPP.org
Questions / Comments spp.issuetrak.com Quick Pick: ICT Planning– Transmission James Lyle English Cook