Download presentation
Presentation is loading. Please wait.
1
P17250: Robofish Charging Station
MSD II Gate Review P17250: Robofish Charging Station
2
Agenda Project Status Schedule Review Issue Management Review
Suggestions for Future Work What Worked Well Lessons Learned Status of Deliverables / Edge
3
Project Status Function Overview Harvest Energy Store Energy
Attach Robofish Dock Robofish Charge Robofish Reliable Structure Stable & Buoyant Protect / House Electronics JM
4
Project Status Table 1: Customer Requirements vs Performance
Table 2: Engineering Requirements vs Performance JM
5
MSD II Schedule Review - Dates
Table 1: Scheduled completion dates vs actual completion dates for major tasks Task Scheduled Completion* Actual Completion Finalize test plan 2/8 2/7 Fix the Robofish N/A Mech. Subsystem - Frame & Connector 2/27 3/1 Mech. Subsystem - Guides 5/4 Elec. Subsystem - Robofish Circuit 2/21 4/11 Elec. Subsystem - RCS Circuit Soft. Subsystems 2/22 Integration of Major Subsystems 3/3 Completion of Test Plan 3/17 5/5 *From original schedule, started on 1/23 JM
6
MSD II Schedule Review - Hours
Table 2: Scheduled hours vs actual hours for a sample of tasks completed Task Scheduled Hours Actual Delta Fix the Robofish 20 >18 * Mech. Subsystem - Frame & Connectors 50 +30 Mech. Subsystem - Guides 15 25 +10 Elec. Subsystem - Robofish Circuit 16 -1 Elec. Subsystem - RCS Circuit 18 >60 +42 Soft. Subsystems 38 40 +2 *Not completed JM
7
Lessons Learned - Jack Obstacle Cause Effect Lesson Learned
Table 3: Jack’s major lessons learned Obstacle Cause Effect Lesson Learned Unclear or non-applicable tasks on schedule Inexperience with certain project tasks Team members felt lost when looking at what they should do next If you do not have experience with a task, work with the person who will be performing it to help define it Time Management / Prioritization ‘Suggested deadlines’ & School work Team placed other work / activities before MSD tasks Set strict deadlines ahead of time for each task Several systems did not work as designed Idealized thinking Schedule fell behind Create prototypes, other feasibility analyses can fall short Other Comments About the Schedule MS Project was an obstacle Schedule too detailed for first experience (~250 tasks) Many tasks were completed by people they were not assigned to Make sure the team knows ahead of time what is expected when tasks are delegated The task due date is not when the first attempt is due JM
8
Issue Management Review
Overall most issues were resolved, and the solution proved to be successful Biggest issues were: RoboFish - see outstanding issues Float/Guide adhesion - tested multiple different types but ultimately found that Velcro adhesive stuck well to the polyethylene floats and will allow future team to change the guides while keeping the floats intact Scheduling pool time Customer communication Outstanding Issues: Most issues reside with the RoboFish not working properly Ran out of time to fully ensure the RoboFish is waterproof This caused us to be unable to fully test our guide and docking system CP
9
Suggestions for Future Work
RoboFish New, larger, more flexible electrical box Remote control Data gathering Investigate Electronics Failures RCS Multiple RoboFish charging Weatherproof Interface with the RoboFish - Communication and/or Docking system JN
10
What worked well Splitting up the team into sections: Electrical, Mechanical, Software Having a variety of skillsets Having a common communication medium (Google Hangouts) and a singular repository that we can all edit (Google Drive) BM
11
Lessons Learned - Lucas
There were pullup resistors in the Arduino that caused the prototype to malfunction. The lesson here is not to expect everything would work the way you want it just because it worked the way you expected before. When shifting to other components, expect there to be issues and use the Serial built into the Arduino to debug everything that could possibly go wrong If you do not know how to do something well, it’s better to ask someone more knowledgeable than messing it up. Afterwards, it’s important to observe and learn from them so you can do it yourself the next time with more confidence. LA
12
Lessons Learned - Chris
To finalize all components in MSD I Order parts sooner Stick to a tighter schedule and ensure tasks are clearly defined Allow us to test sooner Troubleshoot sooner Make necessary changes sooner There will always be issues Communication Pool Access CP
13
Lessons Learned - Brittany
Don’t underestimate shipping costs Don’t underestimate the time it takes to fill out orders When ordering electronics, sometimes it’s best to order extras Plan for unexpected expenses If a special location or service is required, include those costs in the budget For example, lifeguards for pool testing The more sources/references, the better Don’t be afraid to ask for help, whether it be from a classmate, professor, or mentor BM
14
Lessons Learned - Johan
Don’t overestimate work to be done Process is important Get work done earlier than later Make a decision and a plan early, and stick to it. Stop going back and forth about trifles. JN
15
Lessons Learned - Garrett
Breadboard early, breadboard often, and breadboard before you order a PCB Delegate more Make sure delineation of duties is clear to everyone When trying to help someone troubleshoot, start with the basics GB
16
Status of Deliverables and Edge
Should just be a yes/no checklist BM
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.